|
These
terms were
primarily
developed from the Glossary of Terms of the Association for
Project Management and are used with their permission.
Abstract Resource
Imaginary resource introduced so that its availability and
activity requirement gives an extra means of control. (For
example, two jobs not being worked upon simultaneously in order
to obviate an accident hazard)
Acceptance
The formal process of accepting delivery of a product or a
deliverable.
Acceptance
Criteria
Performance requirements and essential conditions that have
to be achieved before project deliverables are accepted.
Acceptance Test
Formal, pre-defined test conducted to determine the
compliance of the deliverable item(s) with the acceptance
criteria.
Accrued Costs
Costs that are earmarked for the project and for which
payment is due, but has not been made.
Acquisition
Strategy
Determining the most appropriate means of procuring the
component parts or services of a project
Activity
Task, job, operation or process consuming time and possibly
other resources. (The smallest self-contained unit of work used
to define the logic of a project. In general, activities share
the following characteristics: a definite duration, logic
relationships to other activities in a project, use resources
such as people, materials or facilities, and have an associated
cost. They should be defined in terms of start and end dates and
the person or organization responsible for their completion.)
Activity
Definition
Identifies the specific activities that must be performed in
order to produce project deliverables.
Activity Duration
Activity duration specifies the length of time (hours, days,
weeks, months) that it takes to complete an activity.
Activity File
A file containing all data related to the definition of
activities on a particular project.
Activity ID
A unique code identifying each activity in a project.
Activity-on-Arrow
Network
Arrow diagram, Network in which the arrows symbolize the
activities.
Activity on Node
Network
Precedence diagram, a network in which the nodes symbolize
the activities.
Activity Status
The state of completion of an activity. A planned activity
has not yet started. A started activity is in progress. A
finished activity is complete.
Actual Cost
Incurred costs that are charged to the project budget and for
which payment has been made, or accrued.
Actual Cost of
Work Performed (ACWP)
Cumulative cost of work accrued on the project in a specific
period or up to a specific stage. Note: for some purposes cost
may be measured in labor hours rather than money.
Actual Dates
Actual dates are entered as the project progresses. These are
the dates that activities really started and finished as opposed
to planned or projected dates.
Actual Direct
Costs
Those costs specifically identified with a contract or
project. See also Direct Costs.
Actual Finish
Date on which an activity was completed.
Actual Start
Date on which an activity was started.
Adjourning
The last stage of team building where the team disbands
Advanced Material
Release
A document used by organizations to initiate the purchase of
long-lead-time or time-critical materials prior to the final
release of a design.
AND Relationship
Logical relationship between two or more activities that
converge on or diverge from an event. Note: The AND relationship
indicates that every one of the activities has to be undertaken.
Approval
The term used when an individual accepts a deliverable as fit
for purpose so that the project can continue.
Approval to
Proceed
Approval given to the project at initiation or prior to the
beginning of the next stage.
Arrow
Directed connecting line between two nodes in a network.
Note 1: It symbolizes an activity in 'activity-on-arrow' Note
2: It symbolizes a dependency relationship in 'activity-on-node'
Arrow Diagram
See 'activity-on-arrow network'.
Arrow Diagram
Method
One of two conventions used to represent an activity in a
project. Also known as Activity-on-Arrow or i/j method.
As-Late-As-Possible (ALAP)
An activity for which the early start date is set late as
possible without delaying the early dates of any successor.
Associated Revenue
That part of a project cost that is of a revenue nature and
therefore charged as incurred to the profit and loss account.
Note: Associated revenue differs from the capital element of the
project in that the capital element is taken as an asset to the
balance sheet and depreciated over future accounting periods.
As-Soon-As-Possible
(ASAP)
An activity for which the early start date is set to be as
soon as possible. This is the default activity type in most
project management systems.
Assumptions
Statements taken for granted or truth.
Audit
Systematic retrospective examination of the whole, or part,
of a project or function to measure conformance with
predetermined standards. Note: Audit is usually qualified, for
example financial audit, quality audit, design audit, project
audit, and health and safety audit.
Authorization
The decision that triggers the allocation of funding needed
to carry on the project
Authorized
Un-priced Work
Any scope change for which authorization to proceed has been
given, but for which the estimated costs are not yet settled.
Authorized Work
The effort which has been defined, plus that work for which
authorization has been given, but for which defined contract
costs have not been agreed upon.
Automatic Decision
Event
Decision event where the decision depends only on the outcome
of the preceding activities and that can be programmed or made
automatic.
Top of Page
Backward Pass
Procedure whereby the latest event times or the latest finish
and start times for the activities of a network are calculated.
Balanced Matrix
An organizational matrix where functions and projects have
the same priority.
Bar Chart
Chart on which activities and their durations are represented
by lines drawn to a common time scale. Note 1: A Gantt chart is
a specific type of bar chart and should not be used as a synonym
for bar chart Note 2: See also ‘cascade chart’.
Baseline
Reference levels against which the project is monitored and
controlled.
Baseline Cost
The amount of money an activity was intended to cost when the
schedule was baselined
Baseline Dates
Original planned start and finished dates for an activity.
Used to compare with current planned dates to determine any
delays. Also used to calculate budgeted cost of work scheduled
for earned-valued analysis.
Baseline Review
A customer review conducted to determine that a contractor is
continuing to use the previously accepted performance system and
is properly implementing a baseline on the contract or option
under review.
Baseline Schedule
The baseline schedule is a fixed project schedule. It is the
standard by which project performance is measured. The current
schedule is copied into the baseline schedule which remains
frozen until it is reset. Resetting the baseline is done when
the scope of the project has been changed significantly, for
example after a negotiated change. At that point, the original
or current baseline becomes invalid and should not be compared
with the current schedule.
Benefits
The enhanced efficiency, economy and effectiveness of future
business or other operations to be delivered by a project or
program.
Benefits Framework
An outline of the expected benefits of the project or
program, the business operations affected and current and target
performance measures.
Benefits
Management
Combined with project or program management, Benefits
Management is the process for planning, managing, delivering and
measuring the project or program benefits.
Benefits
Management Plan
Specifies who is responsible for achieving the benefits set
out in the benefit profiles and how achievement of the benefits
is to be measured, managed and monitored.
Bid
A tender, quotation or any offer to enter into a contract
Bid Analysis
An analysis of bids or tenders.
Bottom Up Cost
Estimating
This is the method of making estimates for every activity in
the work breakdown structure and summarizing them to provide a
total project cost estimate.
Brainstorming
The unstructured generation of ideas by a group of people.
Branching Logic
Conditional logic. Alternative paths in a probabilistic
network.
Breakdown
Structure
A hierarchical structure by which project elements are broken
down, or decomposed. See also Product Breakdown Structure (PBS),
Organizational Breakdown Structure (OBS) and Work Breakdown
Structure (WBS).
Budget
Quantification of resources needed to achieve a task by a set
time, within which the task owners are required to work. Note: A
budget consists of a financial and/or quantitative statement,
prepared and approved prior to a defined period, for the purpose
of attaining a given objective for that period. (The
planned cost for an activity or project.)
Budgetary Control
System of creating budgets, monitoring progress and taking
appropriate action to achieve budgeted performance. Note: A
budget should provide the information necessary to enable
approval, authorization and policy-making bodies to assess a
project proposal and reach a rational decision.
Budget Cost
The cost anticipated at the start of a project.
Budget at
Completion (BAC)
The sum total of the time-phased budgets.
Budgeted Cost of
Work Performed (BCWP)
The planned cost of work completed to date. BCWP is also the
"earned value" of work completed to date.
Budgeted Cost of
Work Scheduled (BCWS)
The planned cost of work that should have been achieved
according to the project baseline dates
Budget Element
Budget elements are the same as resources -- the people,
materials, or other entities needed to do the work Budget
elements can be validated against a Resource Breakdown Structure
(RBS). They are typically assigned to a work package, but can
also be defined at the cost account level.
Budget Estimate
An approximate estimate prepared in the early stages of a
project to establish financial viability or secure resources.
Budgeting
Time phased financial requirements.
Budget Unit
The budget unit is the base unit for the calculation. For
example, the Engineer budget element might have a budget unit of
hours. Since budget units are user defined, they can be any
appropriate unit of measure. For example, a budget unit might be
hours, pounds sterling, linear meters, or tons.
Burden
Overhead expenses distributed over appropriate direct labor
and/or material base.
Business Case
Information necessary to enable approval, authorization and
policy making bodies to assess a project proposal and reach a
reasoned decision
Top of Page
Calendars
A project calendar lists time intervals in which activities
or resources can or cannot be scheduled. A project usually has
one default calendar for the normal workweek (Monday through
Friday for example), but may have other calendars as well. Each
calendar can be customized with its own holidays and extra work
days. Resources and activities can be attached to any of the
calendars that are defined.
Capital Cost
The carrying cost in a balance sheet of acquiring an asset
and bringing it to the condition where it is capable of
performing its intended function over a future series of
periods. Note: See also 'revenue cost'.
Capital Employed
Amount of investment in an organization or project, normally
the sum of fixed and current assets, less current liabilities at
a particular date.
Cascade Chart
Bar chart on which the vertical order of activities is such
that each activity is dependent only on activities higher in the
list.
Cash Flow
Cash receipts and payments in a specified period
Cash Flow, Net
Difference between cash received and payments made during a
specific period.
Champion
An end user representative often seconded into a project
team. Someone who acts as an advocate for a proposal or project
Change Log
A record of all project changes, proposed, authorized or
rejected.
Change Management
The formal process through which changes to the project plan
are approved and introduced.
Change Control
Process that ensures potential changes to the deliverables of
a project or the sequence of work in a project, are recorded,
evaluated, authorized and managed.
Change Control
Board
A formally constituted group of stakeholders responsible for
approving or rejecting changes to the project baselines.
Change Request
A request needed to obtain formal approval for changes to the
scope, design, methods, costs or planned aspects of a project.
Change requests may arise through changes in the business or
issues in the project. Change requests should be logged,
assessed and agreed on before a change to the project can be
made.
Child Activity
Subordinate task belonging to a 'parent' task existing at a
higher level in the Work Breakdown Structure.
Client
The party to a contract who commissions the work and pays for
it on completion.
Close Out
The completion of work on a project.
Closure
The formal end point of a project, either because it has been
completed or because it has been terminated early.
Code of Accounts
Any numbering system, usually based on corporate code of
accounts of the primary performing organization, used to monitor
project costs by category.
Commissioning
Advancement of an installation from the stage of static
completion to full working order and achievement of the
specified operational requirements.
Commitment
A binding financial obligation, typically in the form of a
purchase order or contract.
Committed Costs
Costs that are legally committed even if delivery has not
taken place with invoices neither raised nor paid.
Communication
The transmission of information so that the recipient
understands clearly what the sender intends.
Communications
Planning
Determining project stakeholders’ communication and
information needs.
Completion Date
The date calculated by which the project could finish
following careful estimating.
Compound Risk
A risk made up of a number of inter-related risks.
Conception Phase
The phase that triggers and captures new ideas or
opportunities and identifies potential candidates for further
development in the feasibility phase
Concurrent
Engineering
The systematic approach to the simultaneous, integrated
design of products and their related processes, such as
manufacturing, testing and supporting.
Configuration
Functional and physical characteristics of a product as
defined in technical documents and achieved in the product.
Note: In a project this should contain all items that can be
identified as being relevant to the project and that should only
be modified after authorization by the relevant manager.
(Includes documentation)
Configuration
Audit
A check to ensure that all deliverable items on a project
conform with one another and to the current specification. It
ensures that relevant quality assurance procedures have been
implemented and that there is consistency throughout project
documentation.
Configuration
Control
A system through which changes may be made to configuration
items
Configuration
Identification
Identifies uniquely all items within the configuration
Configuration Item
A part a of configuration that has a set function and is
designated for configuration management. It identifies uniquely
all items within the configuration
Configuration
Management
Technical and administrative activities concerned with the
creation, maintenance and controlled change of configuration
throughout the life of the product. Note: See BS EN ISO 10007
for guidance on configuration management, including specialist
terminology.
Configuration
Status Accounting
Records and reports the current status and history of all
changes to the configuration. Provides a complete record of what
happened to the configuration to date
Conflict
Management
The ability to manage conflict creatively and effectively
Constraints
Applicable restrictions that will affect the scope of the
project or the sequence of project activities.
Consumable
Resource
A type of resource that only remains available until consumed
(for example, a material).
Contingency
A Contingency is the planned allotment of time and cost or
other resources for unforeseeable elements with a project.
Contingency Plan
Mitigation plan. Alternative course(s) of action devised to
cope with project risks. Note: See risk plan
Contingency
Planning
The development of a management plan that uses alternative
strategies to minimize or negate the adverse effects of a risk,
should it occur.
Contract
A mutually binding agreement in which the contractor is
obligated to provide services or products and the buyer is
obligated to provide payment for them. Contracts fall into
three main categories: fixed price, cost reimbursable or unit
price but may contain elements from each.
Contract Budget
Base
The negotiated contract cost value plus the estimated value
of authorized but un-priced work.
Contract Close-out
Settlement of a contract
Contractor
A person, company or firm who holds a contract for carrying
out the works and/or the supply of goods or services in
connection with the project
Contract Target
Cost
The negotiated costs for the original defined contract and
all contractual changes that have been agreed and approved, but
excluding the estimated cost of any authorized, un-priced
changes. The contract target cost equals the value of the budget
at completion plus management or contingency reserve.
Contract Target
Price
The negotiated estimated costs plus profit or fee.
Control
Control is the process of developing targets and plans;
measuring actual performance, comparing it against planned
performance, analyzing the differences and taking effective
action to correct the situation.
Control Charts
Control charts display the results, over time, of a process.
They are used to determine if the process is in need of
adjustment
Coordination
Coordination is the act of ensuring that work carried out by
different organizations and in different places fits together
effectively. It involves technical matters, time, content and
cost in order to achieve the project objectives effectively.
Co-coordinated
Matrix
An organizational structure where the project leader reports
to the functional manager and doesn’t have authority over team
members from other departments
Corrective Action
Changes made to bring future project performance back into
line with the plan.
Cost Account
A cost account defines what work is to be performed who will
perform it and who is to pay for it. Cost accounts are the focal
point for the integration of scope, cost, and schedule. Another
term for Cost Account is Control Account.
Cost Account
Manager
A member of a functional organization responsible for cost
account performance, and for the management of resources to
accomplish such tasks.
Cost Benefit
Analysis
An analysis of the relationship between the costs of
undertaking a task or project, initial and recurrent, and the
benefits likely to arise from the changed situation, initially
and recurrently. Note: The hard, tangible, readily
measurable benefits may sometimes be accompanied by soft
benefits which may be real but difficult to isolate, measure and
value. (Allows comparison of the returns from alternative forms
of investment.)
Cost Breakdown
Structure
Hierarchical breakdown of a project into cost elements.
Cost Budgeting
Allocating cost estimates to individual project components.
Cost Centre
Location, person, activity or project in respect of which
costs may be ascertained and related to cost units.
Cost Code
Unique identity for a specified element of work. (Code
assigned to activities that allow costs to be consolidated
according to the elements of a code structure.)
Cost Control Point
The point within a program at which costs are entered and
controlled. Frequently, the cost control point for a project is
either the cost account or the work package.
Cost Control
System
Any system of keeping costs within the bounds of budgets or
standards based upon work actually performed.
Cost Curve
A graph plotted against a horizontal time scale and
cumulative cost vertical scale.
Cost Element
A unit of costs to perform a task or to acquire an item. The
cost estimated may be a single value or a range of values.
Cost Estimating
The process of predicting the costs of a project.
Cost Incurred
Costs identified through the use of the accrued method of
accounting or costs actually paid. Costs include direct labor,
direct materials, and all allowable indirect costs.
Cost Management
The effective financial control of the project through
evaluating, estimating, budgeting, monitoring, analyzing,
forecasting and reporting the cost information.
Cost Overrun
The amount by which a contractor exceeds or expects to exceed
the estimated costs, and/or the final limitations (the ceiling)
of a contract.
Cost Performance
Index (CPI)
A measure, expressed as a percentage or other ratio of actual
cost to budget plan. (Ratio of work accomplished versus
work cost incurred for a specified time period. The CPI is an
efficiency rating for work accomplished for resources expended.)
Cost Performance
Report
A regular cost report to reflect cost and schedule status
information for management.
Cost Plan
A budget which shows the amounts and expected dates of
incurring costs on the project or on a contract
Cost Plus Fixed
Fee Contract
A type of contract where the buyer reimburses the seller for
the seller’s allowable costs plus a fixed fee.
Cost Plus
Incentive Fee Contract (CPIFC)
A type of Contract where the buyer reimburses the seller for
the seller's allowable costs and the seller earns a profit if
defined criteria are met.
Cost Reimbursement
Type Contracts
A category of contracts based on payments to a contractor for
allowable estimated costs, normally requiring only a "best
efforts" performance standard from the contractor. Risk for
all growth over the estimated value rests with the project
owner.
Cost/Schedule
Planning and Control Specification (C/SPCS)
The United States Air Force initiative in the mid-1960's
which later resulted in the C/SCSC.
Cost –Time
Resource sheet (CTR)
A document that describes each major element in the WBS,
including a Statement of Work (SOW) describing the work content,
resources required, the time frame of the work element and a
cost estimate.
Cost Variance
The difference (positive or negative) between the actual
expenditure and the planned/budgeted expenditure
Credited Resource
Resource that is created by an activity or event and can then
be used by the project.
Critical Activity
An activity is termed critical when it has zero or negative
float.
Criticality Index
Used in risk analysis, the criticality index represents the
percentage of simulation trails that resulted in the activity
being placed on the critical path.
Critical Path
Sequence of activities through a project network from start
to finish, the sum of whose durations determines the overall
project duration. Note: There may be more than one such path.
The path through a series of activities,
taking into account interdependencies, in which the late
completion of activities will have an impact on the project end
date or delay a key milestone.
Critical Path Analysis
Procedure for calculating the critical path
and floats in a network.
Critical Path Method (CPM)
A technique used to predict project
duration by analyzing which sequence of activities has the least
amount of scheduling flexibility. The Critical Path Method is a
modeling process that defines all the project's critical
activities that must be completed on time. The start and finish
dates of activities in the project are calculated in two passes.
The first pass calculates early start and finish dates from the
earliest start date forward. The second pass calculates the late
start and finish activities from the latest finish date
backwards. The difference between the pairs of start and finish
dates for each task is the float or slack time for the task (see
Float). Slack is the amount of time a task can be delayed
without delaying the project completion date. By experimenting
with different logical sequences and /or durations the optimal
project schedule can be determined.
Critical Performance Indicator
A critical factor against which aspects of
project performance may be assessed
Critical Success Factor
A factor considered to be most conducive to
the achievement of a successful project
Customer
Any person, who defines needs or wants,
justifies or pays for part or the entire project, or evaluates
or uses the results. Could be the project promoter, client,
owner or employer
Cut-off Date
The ending date of a reporting period.
Top of Page
Dangle
An activity or network which has either no
predecessors or no successors. If neither, it is referred to as
an isolated activity.
Decision Event
State in the progress of a project when a
decision is required before the start of any succeeding
activity. Note The decision determines which of a number of
alternative paths is to be followed.
Delaying Resource
In resource scheduling, inadequate
availability of one or more resources may require that the
completion of an activity be delayed beyond the date on which it
could otherwise be completed. The delaying resource is the first
resource on an activity that causes the activity to be delayed.
Delegation
The practice of getting others to perform
work effectively which one chooses not to do oneself. The
process by which authority and responsibility is distributed
from Project Manager to subordinates.
Deliberate Decision Event
Decision event where the decision is made
as a result of the outcomes of the preceding activities and
possibly other information but it cannot be made automatically
Deliverables
End products of a project or the measurable
results of intermediate activities within the project
organization Note: Deliverables may be in the form of hardware,
software, services, processes, documents or any combination
thereof.
Delphi Technique
A process where a consensus view is reached
by consultation with experts. Often used as an estimating
technique.
Dependency
Precedence relationship. Restriction that
one activity has to precede, either in part or in total, another
activity. Dependencies are relationships between
products or tasks. For example, one product may be made up of
several other ‘dependent’ products or a task may not begin
until a ‘dependent’ task is complete. See also logical
relationship.
Dependency Arrow
A link arrow used in an activity on node
network to represent the interrelationships of activities in a
project
Design Authority
The person or organization with overall
design responsibility for the products of the project
Design and Development Phase
The time period in which production process
and facility and production processes are developed and
designed.
Deterministic Network
Network containing paths, all of which have
to be followed and whose durations are fixed. Note:
Deterministic network is a term used to distinguish traditional
networking from probabilistic networking
Direct Costs
Costs that are specifically attributable to
an activity or group of activities without apportionment.
(Direct costs are best contrasted with indirect costs that
cannot be identified to a specific project.)
Discounted Cash Flow (DCF)
Concept of relating future cash inflows and
outflows over the life of a project or operation to a common
base value thereby allowing more validity to comparison of
projects with different durations and rates of cash flow.
Discrete Milestone
A milestone that has a definite scheduled
occurrence in time. Logical link that may require time but
no other resource.
Dummy activity in activity on arrow
network
An activity representing no actual work to
be done but required for reasons of logic or nomenclature. Note:
There are three uses for a dummy activity in 'activity-on-arrow
network' a) logic, b) time delay and c) uniqueness.
Duration
Duration is the length of time needed to
complete an activity.
Duration Compression
Often resulting in an increase in cost,
duration compression is the shortening of a project schedule
without reducing the project scope.
Top of Page
Earliest Feasible Date
The earliest date on which the activity
could be scheduled to start based on the scheduled dates of all
its predecessors, but in the absence of any resource constraints
on the activity itself. This date is calculated by resource
scheduling.
Early Dates
Calculated in the forward pass of time
analysis, early dates are the earliest dates on which an
activity can start and finish.
Early Finish
Earliest Finish Time*
Earliest Finish Time
Earliest possible time by which an activity
can finish within the logical and imposed constraints of the
network. (The Early Finish date is defined as the earliest
calculated date on which an activity can end. It is based on the
activity's Early Start which depends on the finish of
predecessor activities and the activity's duration)
Early Start Time
Earliest possible time by which an activity
can start within the logical and imposed constraints of the
network.
Earned Hours
The time in standard hours credited as a
result of the completion of a given task or a group of tasks.
Earned Value
The value of the useful work done at any
given point in a project. Note: The budget may be
expressed in cost or labor hours.
Earned Value Analysis
Analysis of project progress where the
actual money, hours (or other measure) budgeted and spent is
compared to the value of the work achieved.
Earned Value Cost Control
The quantification of the overall progress
of a project in financial terms so as to provide a realistic
yardstick against which to compare the actual cost to date.
Earned Value Management
Earned Value Analysis
Earned Value Analysis
Technique for assessing whether the earned
value in relation to the amount of work completed, is ahead, on,
or behind plan.
Effort
The number of labor units necessary to
complete the work. Effort is usually expressed in staff-hours,
staff-days or staff-weeks and should not be confused with
duration.
Effort-Driven Activity
An activity whose duration is governed by
resource usage and availability. The resource requiring the
greatest time to complete the specified amount of work on the
activity will determine its duration.
Effort Remaining
The estimate of effort remaining to
complete an activity.
Elapsed Time
Elapsed time is the total number of
calendar days (excluding non-work days such as weekends or
holidays) that is needed to complete an activity. It gives a
realistic view of how long an activity is scheduled to take for
completion.
End Activity
An activity with no logical successors.
End Event (of a project)
Event with preceding, but no succeeding
activities. Note: There may be more than one end event.
Environmental Factoring
Use of data relating to an external factor
(such as the weather) to modify or bias the value of parameters
concerned.
Equivalent Activity
Activity that is equivalent, in the
probabilistic sense, to any combination of series and parallel
activities.
Estimate
A quantified assessment of the resources
required to complete part or all of a project. The prediction of
the quantitative result. It is usually applied to project costs,
resources and durations.
Estimate At Completion (EAC)
A value expressed in either money and /or
hours, to represent the projected final costs of work when
completed. The EAC is calculated as ETC + ACWP.
Estimate To Complete (ETC)
The value expressed in either money or
hours developed to represent the cost of the work required to
complete a task.
Estimating
The act of combining the results of post
project reviews, metrics, consultation and informed assessment
to arrive at time and resource requirements for an activity.
Event
State in the progress of a project after
the completion of all preceding activities, but before the start
of any succeeding activity. (A defined point that is the
beginning or end of an activity)
Exception Report
Focused report drawing attention to
instances where planned and actual results are expected to be,
or are already, significantly different. Note: An exception
report is usually triggered when actual values are expected to
cross a predetermined threshold that is set with reference to
the project plan The actual values may be trending better or
worse than plan.
Exclusive OR Relationship
Logical relationship indicating that only
one of the possible activities can be undertaken.
Execution phase
The phase of a project in which work
towards direct achievement of the project’s objectives and the
production of the project’s deliverables occurs. Sometimes
called the implementation phase
Expenditure
A charge against available funds, evidenced
by a voucher, claim, or other documents. Expenditures represent
the actual payment of funds.
Exceptions
Exceptions are occurrences that cause
deviation from a plan, such as issues, change requests and
risks. Exceptions can also refer to items where the cost
variance and schedule variance exceed predefined thresholds.
External Constraint
A constraint from outside the project
network.
Top of Page
Fast–Tracking
Reducing the duration of a project usually
by overlapping phases or activities that were originally planned
to be done sequentially. (The process of reducing the
number of sequential relationships and replacing them typically
with parallel relationships (usually to achieve shorter overall
durations but often with increased risk)).
Fallback Plan
A plan for an alternative course of action
that can be adopted to overcome the consequences of a risk,
should it occur (including carrying out any advance activities
that may be required to render the plan practical)
Feasibility Phase
The project phase that demonstrates that
the client's requirement can be achieved and identifies and
evaluates the options to determine the one preferred solution
Feasibility Study
Analysis to determine if a course of action
is possible within the terms of reference of the project.
Feasible schedule
Any schedule capable of implementation
within the externally determined constraints of time and/or
resource limits.
Final Report
Post-implementation report. Normally a
retrospective report that formally closes the project having
handed over the project deliverables for operational use Note:
The report should draw attention to experiences that may be of
benefit to future projects and may form part of the
accountability of the project team
Finish Date
The actual or estimated time associated
with an activity’s completion.
Finishing Activity
A finishing activity is the last activity
that must be completed before a project can be considered
finished. This activity is not a predecessor to any other
activity -- it has no successors.
Finish-To-Finish Lag
The finish-to-finish lag is the minimum
amount of time that must pass between the finish of one activity
and the finish of its successor(s)
Finish-To-Start Lag
The finish-to-start lag is the minimum
amount of time that must pass between the finish of one activity
and the start of its successor(s). The default finish-to-start
lag is zero.
Firm Fixed Price Contract
A contract where the buyer pays a set
amount to the seller regardless of that seller’s cost to
complete the contract.
Fixed Date
A calendar date (associated with a plan)
that cannot be moved or changed during the schedule.
Fixed-Duration Scheduling
A scheduling method in which, regardless of
the number of resources assigned to the task, the duration
remains the same.
Fixed Finish
See Imposed Finish.
Fixed Price Contracts
A generic category of contracts based on
the establishment of firm legal commitments to complete the
required work. A performing contractor is legally obligated to
finish the job, no matter how much it costs to complete. Risks
of all cost growth rest on the performing contractor.
Fixed Start
See Imposed Start.
Float
Time available for an activity or path in
addition to its planned duration. (Float is the amount of
time that an activity can slip past its earliest completion date
without delaying the rest of the project. The calculation
depends on the float type. See start float, finish float, free
float, positive float, and negative float)
Forecast At Completion
Scheduled cost for a task.
Forecast Final Cost
See Estimate at Completion.
Forward Pass
A procedure whereby the earliest event
times or the earliest start and finish times for the activities
of a network are calculated.
Free Float
Time by which an activity may be delayed or
extended without affecting the start of any succeeding activity.
Note: free float can never be negative.
Functional Organization
Management structure where specific
functions of an organization are grouped into specialist
departments providing dedicated services. Note: Examples of
functional organization are finance, marketing and design
departments.
Functional Specification
A document specifying in some detail the
functions that are required of a system and the constraints that
will apply
Functional Manager
The person responsible for the business and
technical management of a functional group.
Functional Matrix
An organization type where the project has
a team leader in each functional department and the products are
passed from one team to the next.
Functional Organization
A functional management structure where
specific functions of a business are grouped into specialist
departments that provide a dedicated service to the whole of the
organization e.g. accounts department, production department,
drawing office.
Funding Profile
An estimate of funding requirements over
time.
Top of Page
Gantt Chart
Particular type of bar chart showing
planned activity against time. Note: 'Gantt Chart',
although named for a particular type of bar chart, is in current
usage as a name for bar charts in general. (A Gantt chart is a
time-phased graphic display of activity durations. Activities
are listed with other tabular information on the left side with
time intervals over the bars. Activity durations are shown in
the form of horizontal bars.)
Goal
A one-sentence definition of specifically
what will be accomplished, while incorporating an event
signifying completion.
Top of Page
Hammock
Activity, joining two specified points,
that span two or more activities. Note: Its duration is
initially unspecified and is only determined by the durations of
the specified activities. Note: Hammocks are usually used to
collect time-dependent information, e.g. overheads. (A group of
activities, milestones, or other hammocks aggregated together
for analysis or reporting purposes. Sometimes used to describe
an activity such as management support that has no duration of
its own but derives one from the time difference between the two
points to which it is connected)
Hand-over
The formal process of transferring
responsibility for and ownership of the products of a project to
the operator or owner
Hierarchical Coding Structure
A coding system that can be represented as
a multi-level tree structure in which every code except those at
the top of the tree has a parent code.
Hierarchy of Networks
Range of networks at different levels of
detail, from summary down to working levels, showing the
relationships between those networks
Histogram
A graphic display of planned and or actual
resource usage over a period of time. It is in the form of a
vertical bar chart, the height of each bar representing the
quantity of resource usage in a given time unit. Bars may be
single, multiple or show stacked resources.
Holiday
An otherwise valid working day that has
been designated as exempt from work.
Host Organization
Organization that provides the
administrative and logistical support for the project.
Hypercritical Activities
Activities on the critical path with
negative float.
Top of Page
Impact
The assessment of the adverse effects of an
occurring risk.
Impact Analysis
Assessing the merits of pursuing a
particular course of action.
Implementation Phase
The project phase that develops the chosen
solution into a completed deliverable. (Note: Realization is the
internationally accepted and preferred term for implementation)
Imposed Date
Point in time determined by circumstances
outside the network. Note: A symbol is inserted immediately
above the event concerned on activity on arrow networks or
adjacent and connected to the appropriate corner of the node on
activity on node networks
Imposed Finish
A finished date imposed on an activity by
external constraints.
Imposed Start
A start date imposed on an activity by
external constraints.
Inclusive OR relationship
Logical relationship indicating that at
least one but not necessarily all of the activities have to be
undertaken
INCOTERMS
A set of international terms defining
conditions for delivery and shipping of equipment and materials
Incurred Costs
Sum of actual and committed costs, whether
invoiced/paid or not, at a specified time
Indirect Cost
Costs associated with a project that cannot
be directly attributed to an activity or group of activities.
(Resources expended which are not directly identified to any
specific contract, project, product or service, such as
overheads and general administration)
In-house Project
A project commissioned and carried out
entirely within a single organization
Initiation
Committing the organization to begin a
project.
In Progress
An activity that has been started, but not
yet completed.
Integrated Logistics Support
Disciplined approach to activities
necessary to a) cause support considerations to be
integrated into product design b) develop support
arrangements that are consistently related to design and to each
other and c) provide the necessary support at the
beginning and during customer use at optimum cost.
Integration
The process of bringing people, activities
and other things together to perform effectively.
Internal Rate of Return (IRR)
Discount rate at which the net present
value of a future cash flow is zero. Note: IRR is a special case
of the ‘discounted cash flow’ procedures.
Inverted Matrix
A project oriented organization structure
that employs permanent specialists to support projects
Issue
An immediate problem requiring resolution
Top of Page
Key Events
Major events the achievement of which that
are deemed to be critical to the execution of the project
Key Performance Indicators
Measurable indicators that will be used to
report progress that is chosen to reflect the critical success
factors of the project.
Top of Page
Labor Rate Variances
Difference between planned labor rates and
actual labor rates.
Ladder
Device for representing a set of
overlapping activities in a network diagram. Note: The start and
finish of each succeeding activity are linked only to the start
and finish of the preceding activity by lead and lag activities,
which consume only time.
Lag
a) In a network diagram, the minimum
necessary lapse of time between the finish of one activity and
the finish of an overlapping activity b) delay incurred between
two specified activities
Late Dates
Calculated in the backward pass of time
analysis, late dates are the latest dates by which an activity
can be allowed to start or finish.
Latest Event Time
Latest time by which an event has to occur
within the logical and imposed constraints of the network,
without affecting the total project duration
Late Event Date
Calculated from backward pass, it is the
latest date an event can occur.
Latest Finish Time
The latest possible time by which an
activity has to finish within the logical activity and imposed
constraints of the network, without affecting the total project
duration
Latest Start Time
Latest possible time by which an activity
has to start within the logical and imposed constraints of the
network, without affecting the total project duration
Lead
In a network diagram, the minimum necessary
lapse of time between the start of one activity and the start of
an overlapping activity
Lead Contractor
The contractor who has responsibility for
overall project management and quality assurance
Leadership
Getting others to follow
Letter of Intent
A letter indicating an intent to sign a
contract, usually so that work can commence prior to signing
that contract.
Leveling
See Resource Leveling.
Life Cycle
A sequence of defined stages over the full
duration of a project
Life-Cycle Costing
When evaluating alternatives, Life-Cycle
Costing is the concept of including acquisition, operating and
disposal costs.
Likelihood
Assessment of the probability that a risk
will occur.
Line Manager
The manager of any group that makes a
product or performs a service.
Linked Bar Chart
A bar chart that shows the dependency links
between activities
Logic
See Network Logic.
Logic Diagram
A diagram that displays the logical
relationships between project activities
Logical Relationship
A logical relationship is based on the
dependency between two project activities or between a project
activity and a milestone.
Loop
An error in a network which results in a
later activity imposing a logical restraint on an earlier
activity
Top of Page
Management by Project
A term used to describe normal management
processes that are being project managed.
Management Development
All aspects of staff planning, recruitment,
development, training and assessment.
Management Reserve
A central contingency pool. Sum of money
held as an overall contingency to cover the cost impact of some
unexpected event occurring. Note: This is self-insurance
Master Network
Network showing the complete project, from
which more detailed networks are derived
Master Schedule
A high level summary project schedule that
identifies major activities and milestones.
Material
Property which may be incorporated into or
attached to an end item to be delivered under a contract or
which may be consumed or expended in the performance of a
contract. It includes, but is not limited to raw and processed
material, parts, components, assemblies, fuels and lubricants,
and small tools and supplies which may be consumed in normal use
in the performance of a contract.
Matrix Organization
An organizational structure where the
Project Manager and the Functional Managers share the
responsibility of assigning priorities and for directing the
work.
Methodology
A documented process for management of
projects that contains procedures, definitions and roles and
responsibilities.
Mid-Stage Assessment
An assessment in the middle of a project
that can be held for several reasons: 1) at the request of
the project board; 2) to authorize work on the next stage before
current one is completed; 3) to allow for a formal review in the
middle of a long project; or 4) to review exception plans.
Milestone
A key event. An event selected for its
importance in the project. Note: Milestones are commonly used in
relation to progress. (A milestone is often chosen to represent
the start of a new phase or completion of a major deliverable.
They are used to monitor progress at summary level. Milestones
are activities of zero duration)
Milestone Plan
A plan containing only milestones which
highlight key points of the project.
Milestone Schedule
A schedule that identifies the major
milestones. See also Master Schedule.
Mission Statement
Brief summary, approximately one or two
sentences, that sums up the background, purposes and benefits of
the project.
Mitigation
Working to reduce risk by lowering its
chances of occurring or by reducing its effect if it occurs.
Mobilization
The bringing together of project personnel
and securing equipment and facilities. Carried out during
project start-up phases
Monitoring
Monitoring is the recording, analyzing and
reporting of project performance as compared to the plan.
Monte Carlo Simulation
A technique used to estimate the likely
range of outcomes from a complex process by simulating the
process under randomly selected conditions a large number of
times.
Multi-Project
A project consisting of multiple
subprojects.
Multi-Project Analysis
Multi-project analysis is used to analyze
the impact and interaction of activities and resources whose
progress affects the progress of a group of projects or for
projects with shared resources or both. Multi-project analysis
can also be used for composite reporting on projects having no
dependencies or resources in common.
Multi-Project Management
Managing multiple projects that are
interconnected either logically or by shared resources.
Multi-project Scheduling
Use of the techniques of resource
allocation to schedule more than one project concurrently
Top of Page
Near-Critical Activity
A low total float activity.
Negative Total Float
Time by which the duration of an activity
or path has to be reduced in order to permit a limiting imposed
date to be achieved
Negotiated Contract Cost
The estimated cost negotiated in a
Cost-Plus-Fixed-Fee Contract or the negotiated contract target
cost in either a Fixed Price-Incentive Contract or a
Cost-Plus-Incentive-Fee Contract. See also Contract Target Cost.
Negotiation
The art of satisfying needs by reaching
agreement or compromise with other parties.
Net Present Value
Aggregate of future net cash flows
discounted back to a common base date, usually the present
Network
A pictorial presentation of project data in
which the project logic is the main determinant of the
placements of the activities in the drawing. Frequently called a
flowchart, PERT chart, logic drawing, or logic diagram.
Network Analysis
Method used for calculating a project's
critical path and activity times and floats. Note: See also
critical path analysis, project network techniques.
Network Interface
Activity or event common to two or more
network diagrams
Network Logic
The collection of activity dependencies
that make up a project network.
Network Path
A series of connected activities in a
project network.
Nodes
Points in a network at which arrows start
and finish
Non-recurring Costs
Expenditures against specific tasks that
are expected to occur only once on a given project.
Non-splittable Activity
An activity that, once started, has to be
completed to plan without interruption. Note: Resources should
not be diverted from a non-splittable activity to another
activity
Not Earlier Than
A restriction on an activity that indicates
that it may not start or end earlier than a specified date.
Not Later Than
A restriction on an activity that indicates
that it may not start or end later than a specified date.
Top of Page
Objectives
Predetermined results toward which effort
is directed.
Operation Phase
Period when the completed deliverable is
used and maintained in service for its intended purpose
Opportunity
The opposite of a risk. The chance to
enhance the project benefits
Order of Magnitude Estimate
An estimate carried out to give very
approximate indication of likely out-turn costs.
Organization Design
The design of the most appropriate
organizational design for a project.
Organizational Breakdown Structure
(OBS)
Hierarchical way in which the organization
may be divided into management levels and groups, for planning
and control purposes
|