|
These
terms were
primarily
developed from the Glossary of Terms of the Association for
Project Management and are used with their permission.
Abstract Resource
Imaginary resource introduced so that its availability and
activity requirement gives an extra means of control. (For
example, two jobs not being worked upon simultaneously in order
to obviate an accident hazard)
Acceptance
The formal process of accepting delivery of a product or a
deliverable.
Acceptance
Criteria
Performance requirements and essential conditions that have
to be achieved before project deliverables are accepted.
Acceptance Test
Formal, pre-defined test conducted to determine the
compliance of the deliverable item(s) with the acceptance
criteria.
Accrued Costs
Costs that are earmarked for the project and for which
payment is due, but has not been made.
Acquisition
Strategy
Determining the most appropriate means of procuring the
component parts or services of a project
Activity
Task, job, operation or process consuming time and possibly
other resources. (The smallest self-contained unit of work used
to define the logic of a project. In general, activities share
the following characteristics: a definite duration, logic
relationships to other activities in a project, use resources
such as people, materials or facilities, and have an associated
cost. They should be defined in terms of start and end dates and
the person or organization responsible for their completion.)
Activity
Definition
Identifies the specific activities that must be performed in
order to produce project deliverables.
Activity Duration
Activity duration specifies the length of time (hours, days,
weeks, months) that it takes to complete an activity.
Activity File
A file containing all data related to the definition of
activities on a particular project.
Activity ID
A unique code identifying each activity in a project.
Activity-on-Arrow
Network
Arrow diagram, Network in which the arrows symbolize the
activities.
Activity on Node
Network
Precedence diagram, a network in which the nodes symbolize
the activities.
Activity Status
The state of completion of an activity. A planned activity
has not yet started. A started activity is in progress. A
finished activity is complete.
Actual Cost
Incurred costs that are charged to the project budget and for
which payment has been made, or accrued.
Actual Cost of
Work Performed (ACWP)
Cumulative cost of work accrued on the project in a specific
period or up to a specific stage. Note: for some purposes cost
may be measured in labor hours rather than money.
Actual Dates
Actual dates are entered as the project progresses. These are
the dates that activities really started and finished as opposed
to planned or projected dates.
Actual Direct
Costs
Those costs specifically identified with a contract or
project. See also Direct Costs.
Actual Finish
Date on which an activity was completed.
Actual Start
Date on which an activity was started.
Adjourning
The last stage of team building where the team disbands
Advanced Material
Release
A document used by organizations to initiate the purchase of
long-lead-time or time-critical materials prior to the final
release of a design.
AND Relationship
Logical relationship between two or more activities that
converge on or diverge from an event. Note: The AND relationship
indicates that every one of the activities has to be undertaken.
Approval
The term used when an individual accepts a deliverable as fit
for purpose so that the project can continue.
Approval to
Proceed
Approval given to the project at initiation or prior to the
beginning of the next stage.
Arrow
Directed connecting line between two nodes in a network.
Note 1: It symbolizes an activity in 'activity-on-arrow' Note
2: It symbolizes a dependency relationship in 'activity-on-node'
Arrow Diagram
See 'activity-on-arrow network'.
Arrow Diagram
Method
One of two conventions used to represent an activity in a
project. Also known as Activity-on-Arrow or i/j method.
As-Late-As-Possible (ALAP)
An activity for which the early start date is set late as
possible without delaying the early dates of any successor.
Associated Revenue
That part of a project cost that is of a revenue nature and
therefore charged as incurred to the profit and loss account.
Note: Associated revenue differs from the capital element of the
project in that the capital element is taken as an asset to the
balance sheet and depreciated over future accounting periods.
As-Soon-As-Possible
(ASAP)
An activity for which the early start date is set to be as
soon as possible. This is the default activity type in most
project management systems.
Assumptions
Statements taken for granted or truth.
Audit
Systematic retrospective examination of the whole, or part,
of a project or function to measure conformance with
predetermined standards. Note: Audit is usually qualified, for
example financial audit, quality audit, design audit, project
audit, and health and safety audit.
Authorization
The decision that triggers the allocation of funding needed
to carry on the project
Authorized
Un-priced Work
Any scope change for which authorization to proceed has been
given, but for which the estimated costs are not yet settled.
Authorized Work
The effort which has been defined, plus that work for which
authorization has been given, but for which defined contract
costs have not been agreed upon.
Automatic Decision
Event
Decision event where the decision depends only on the outcome
of the preceding activities and that can be programmed or made
automatic.
Top of Page
Backward Pass
Procedure whereby the latest event times or the latest finish
and start times for the activities of a network are calculated.
Balanced Matrix
An organizational matrix where functions and projects have
the same priority.
Bar Chart
Chart on which activities and their durations are represented
by lines drawn to a common time scale. Note 1: A Gantt chart is
a specific type of bar chart and should not be used as a synonym
for bar chart Note 2: See also ‘cascade chart’.
Baseline
Reference levels against which the project is monitored and
controlled.
Baseline Cost
The amount of money an activity was intended to cost when the
schedule was baselined
Baseline Dates
Original planned start and finished dates for an activity.
Used to compare with current planned dates to determine any
delays. Also used to calculate budgeted cost of work scheduled
for earned-valued analysis.
Baseline Review
A customer review conducted to determine that a contractor is
continuing to use the previously accepted performance system and
is properly implementing a baseline on the contract or option
under review.
Baseline Schedule
The baseline schedule is a fixed project schedule. It is the
standard by which project performance is measured. The current
schedule is copied into the baseline schedule which remains
frozen until it is reset. Resetting the baseline is done when
the scope of the project has been changed significantly, for
example after a negotiated change. At that point, the original
or current baseline becomes invalid and should not be compared
with the current schedule.
Benefits
The enhanced efficiency, economy and effectiveness of future
business or other operations to be delivered by a project or
program.
Benefits Framework
An outline of the expected benefits of the project or
program, the business operations affected and current and target
performance measures.
Benefits
Management
Combined with project or program management, Benefits
Management is the process for planning, managing, delivering and
measuring the project or program benefits.
Benefits
Management Plan
Specifies who is responsible for achieving the benefits set
out in the benefit profiles and how achievement of the benefits
is to be measured, managed and monitored.
Bid
A tender, quotation or any offer to enter into a contract
Bid Analysis
An analysis of bids or tenders.
Bottom Up Cost
Estimating
This is the method of making estimates for every activity in
the work breakdown structure and summarizing them to provide a
total project cost estimate.
Brainstorming
The unstructured generation of ideas by a group of people.
Branching Logic
Conditional logic. Alternative paths in a probabilistic
network.
Breakdown
Structure
A hierarchical structure by which project elements are broken
down, or decomposed. See also Product Breakdown Structure (PBS),
Organizational Breakdown Structure (OBS) and Work Breakdown
Structure (WBS).
Budget
Quantification of resources needed to achieve a task by a set
time, within which the task owners are required to work. Note: A
budget consists of a financial and/or quantitative statement,
prepared and approved prior to a defined period, for the purpose
of attaining a given objective for that period. (The
planned cost for an activity or project.)
Budgetary Control
System of creating budgets, monitoring progress and taking
appropriate action to achieve budgeted performance. Note: A
budget should provide the information necessary to enable
approval, authorization and policy-making bodies to assess a
project proposal and reach a rational decision.
Budget Cost
The cost anticipated at the start of a project.
Budget at
Completion (BAC)
The sum total of the time-phased budgets.
Budgeted Cost of
Work Performed (BCWP)
The planned cost of work completed to date. BCWP is also the
"earned value" of work completed to date.
Budgeted Cost of
Work Scheduled (BCWS)
The planned cost of work that should have been achieved
according to the project baseline dates
Budget Element
Budget elements are the same as resources -- the people,
materials, or other entities needed to do the work Budget
elements can be validated against a Resource Breakdown Structure
(RBS). They are typically assigned to a work package, but can
also be defined at the cost account level.
Budget Estimate
An approximate estimate prepared in the early stages of a
project to establish financial viability or secure resources.
Budgeting
Time phased financial requirements.
Budget Unit
The budget unit is the base unit for the calculation. For
example, the Engineer budget element might have a budget unit of
hours. Since budget units are user defined, they can be any
appropriate unit of measure. For example, a budget unit might be
hours, pounds sterling, linear meters, or tons.
Burden
Overhead expenses distributed over appropriate direct labor
and/or material base.
Business Case
Information necessary to enable approval, authorization and
policy making bodies to assess a project proposal and reach a
reasoned decision
Top of Page
Calendars
A project calendar lists time intervals in which activities
or resources can or cannot be scheduled. A project usually has
one default calendar for the normal workweek (Monday through
Friday for example), but may have other calendars as well. Each
calendar can be customized with its own holidays and extra work
days. Resources and activities can be attached to any of the
calendars that are defined.
Capital Cost
The carrying cost in a balance sheet of acquiring an asset
and bringing it to the condition where it is capable of
performing its intended function over a future series of
periods. Note: See also 'revenue cost'.
Capital Employed
Amount of investment in an organization or project, normally
the sum of fixed and current assets, less current liabilities at
a particular date.
Cascade Chart
Bar chart on which the vertical order of activities is such
that each activity is dependent only on activities higher in the
list.
Cash Flow
Cash receipts and payments in a specified period
Cash Flow, Net
Difference between cash received and payments made during a
specific period.
Champion
An end user representative often seconded into a project
team. Someone who acts as an advocate for a proposal or project
Change Log
A record of all project changes, proposed, authorized or
rejected.
Change Management
The formal process through which changes to the project plan
are approved and introduced.
Change Control
Process that ensures potential changes to the deliverables of
a project or the sequence of work in a project, are recorded,
evaluated, authorized and managed.
Change Control
Board
A formally constituted group of stakeholders responsible for
approving or rejecting changes to the project baselines.
Change Request
A request needed to obtain formal approval for changes to the
scope, design, methods, costs or planned aspects of a project.
Change requests may arise through changes in the business or
issues in the project. Change requests should be logged,
assessed and agreed on before a change to the project can be
made.
Child Activity
Subordinate task belonging to a 'parent' task existing at a
higher level in the Work Breakdown Structure.
Client
The party to a contract who commissions the work and pays for
it on completion.
Close Out
The completion of work on a project.
Closure
The formal end point of a project, either because it has been
completed or because it has been terminated early.
Code of Accounts
Any numbering system, usually based on corporate code of
accounts of the primary performing organization, used to monitor
project costs by category.
Commissioning
Advancement of an installation from the stage of static
completion to full working order and achievement of the
specified operational requirements.
Commitment
A binding financial obligation, typically in the form of a
purchase order or contract.
Committed Costs
Costs that are legally committed even if delivery has not
taken place with invoices neither raised nor paid.
Communication
The transmission of information so that the recipient
understands clearly what the sender intends.
Communications
Planning
Determining project stakeholders’ communication and
information needs.
Completion Date
The date calculated by which the project could finish
following careful estimating.
Compound Risk
A risk made up of a number of inter-related risks.
Conception Phase
The phase that triggers and captures new ideas or
opportunities and identifies potential candidates for further
development in the feasibility phase
Concurrent
Engineering
The systematic approach to the simultaneous, integrated
design of products and their related processes, such as
manufacturing, testing and supporting.
Configuration
Functional and physical characteristics of a product as
defined in technical documents and achieved in the product.
Note: In a project this should contain all items that can be
identified as being relevant to the project and that should only
be modified after authorization by the relevant manager.
(Includes documentation)
Configuration
Audit
A check to ensure that all deliverable items on a project
conform with one another and to the current specification. It
ensures that relevant quality assurance procedures have been
implemented and that there is consistency throughout project
documentation.
Configuration
Control
A system through which changes may be made to configuration
items
Configuration
Identification
Identifies uniquely all items within the configuration
Configuration Item
A part a of configuration that has a set function and is
designated for configuration management. It identifies uniquely
all items within the configuration
Configuration
Management
Technical and administrative activities concerned with the
creation, maintenance and controlled change of configuration
throughout the life of the product. Note: See BS EN ISO 10007
for guidance on configuration management, including specialist
terminology.
Configuration
Status Accounting
Records and reports the current status and history of all
changes to the configuration. Provides a complete record of what
happened to the configuration to date
Conflict
Management
The ability to manage conflict creatively and effectively
Constraints
Applicable restrictions that will affect the scope of the
project or the sequence of project activities.
Consumable
Resource
A type of resource that only remains available until consumed
(for example, a material).
Contingency
A Contingency is the planned allotment of time and cost or
other resources for unforeseeable elements with a project.
Contingency Plan
Mitigation plan. Alternative course(s) of action devised to
cope with project risks. Note: See risk plan
Contingency
Planning
The development of a management plan that uses alternative
strategies to minimize or negate the adverse effects of a risk,
should it occur.
Contract
A mutually binding agreement in which the contractor is
obligated to provide services or products and the buyer is
obligated to provide payment for them. Contracts fall into
three main categories: fixed price, cost reimbursable or unit
price but may contain elements from each.
Contract Budget
Base
The negotiated contract cost value plus the estimated value
of authorized but un-priced work.
Contract Close-out
Settlement of a contract
Contractor
A person, company or firm who holds a contract for carrying
out the works and/or the supply of goods or services in
connection with the project
Contract Target
Cost
The negotiated costs for the original defined contract and
all contractual changes that have been agreed and approved, but
excluding the estimated cost of any authorized, un-priced
changes. The contract target cost equals the value of the budget
at completion plus management or contingency reserve.
Contract Target
Price
The negotiated estimated costs plus profit or fee.
Control
Control is the process of developing targets and plans;
measuring actual performance, comparing it against planned
performance, analyzing the differences and taking effective
action to correct the situation.
Control Charts
Control charts display the results, over time, of a process.
They are used to determine if the process is in need of
adjustment
Coordination
Coordination is the act of ensuring that work carried out by
different organizations and in different places fits together
effectively. It involves technical matters, time, content and
cost in order to achieve the project objectives effectively.
Co-coordinated
Matrix
An organizational structure where the project leader reports
to the functional manager and doesn’t have authority over team
members from other departments
Corrective Action
Changes made to bring future project performance back into
line with the plan.
Cost Account
A cost account defines what work is to be performed who will
perform it and who is to pay for it. Cost accounts are the focal
point for the integration of scope, cost, and schedule. Another
term for Cost Account is Control Account.
Cost Account
Manager
A member of a functional organization responsible for cost
account performance, and for the management of resources to
accomplish such tasks.
Cost Benefit
Analysis
An analysis of the relationship between the costs of
undertaking a task or project, initial and recurrent, and the
benefits likely to arise from the changed situation, initially
and recurrently. Note: The hard, tangible, readily
measurable benefits may sometimes be accompanied by soft
benefits which may be real but difficult to isolate, measure and
value. (Allows comparison of the returns from alternative forms
of investment.)
Cost Breakdown
Structure
Hierarchical breakdown of a project into cost elements.
Cost Budgeting
Allocating cost estimates to individual project components.
Cost Centre
Location, person, activity or project in respect of which
costs may be ascertained and related to cost units.
Cost Code
Unique identity for a specified element of work. (Code
assigned to activities that allow costs to be consolidated
according to the elements of a code structure.)
Cost Control Point
The point within a program at which costs are entered and
controlled. Frequently, the cost control point for a project is
either the cost account or the work package.
Cost Control
System
Any system of keeping costs within the bounds of budgets or
standards based upon work actually performed.
Cost Curve
A graph plotted against a horizontal time scale and
cumulative cost vertical scale.
Cost Element
A unit of costs to perform a task or to acquire an item. The
cost estimated may be a single value or a range of values.
Cost Estimating
The process of predicting the costs of a project.
Cost Incurred
Costs identified through the use of the accrued method of
accounting or costs actually paid. Costs include direct labor,
direct materials, and all allowable indirect costs.
Cost Management
The effective financial control of the project through
evaluating, estimating, budgeting, monitoring, analyzing,
forecasting and reporting the cost information.
Cost Overrun
The amount by which a contractor exceeds or expects to exceed
the estimated costs, and/or the final limitations (the ceiling)
of a contract.
Cost Performance
Index (CPI)
A measure, expressed as a percentage or other ratio of actual
cost to budget plan. (Ratio of work accomplished versus
work cost incurred for a specified time period. The CPI is an
efficiency rating for work accomplished for resources expended.)
Cost Performance
Report
A regular cost report to reflect cost and schedule status
information for management.
Cost Plan
A budget which shows the amounts and expected dates of
incurring costs on the project or on a contract
Cost Plus Fixed
Fee Contract
A type of contract where the buyer reimburses the seller for
the seller’s allowable costs plus a fixed fee.
Cost Plus
Incentive Fee Contract (CPIFC)
A type of Contract where the buyer reimburses the seller for
the seller's allowable costs and the seller earns a profit if
defined criteria are met.
Cost Reimbursement
Type Contracts
A category of contracts based on payments to a contractor for
allowable estimated costs, normally requiring only a "best
efforts" performance standard from the contractor. Risk for
all growth over the estimated value rests with the project
owner.
Cost/Schedule
Planning and Control Specification (C/SPCS)
The United States Air Force initiative in the mid-1960's
which later resulted in the C/SCSC.
Cost –Time
Resource sheet (CTR)
A document that describes each major element in the WBS,
including a Statement of Work (SOW) describing the work content,
resources required, the time frame of the work element and a
cost estimate.
Cost Variance
The difference (positive or negative) between the actual
expenditure and the planned/budgeted expenditure
Credited Resource
Resource that is created by an activity or event and can then
be used by the project.
Critical Activity
An activity is termed critical when it has zero or negative
float.
Criticality Index
Used in risk analysis, the criticality index represents the
percentage of simulation trails that resulted in the activity
being placed on the critical path.
Critical Path
Sequence of activities through a project network from start
to finish, the sum of whose durations determines the overall
project duration. Note: There may be more than one such path.
The path through a series of activities,
taking into account interdependencies, in which the late
completion of activities will have an impact on the project end
date or delay a key milestone.
Critical Path Analysis
Procedure for calculating the critical path
and floats in a network.
Critical Path Method (CPM)
A technique used to predict project
duration by analyzing which sequence of activities has the least
amount of scheduling flexibility. The Critical Path Method is a
modeling process that defines all the project's critical
activities that must be completed on time. The start and finish
dates of activities in the project are calculated in two passes.
The first pass calculates early start and finish dates from the
earliest start date forward. The second pass calculates the late
start and finish activities from the latest finish date
backwards. The difference between the pairs of start and finish
dates for each task is the float or slack time for the task (see
Float). Slack is the amount of time a task can be delayed
without delaying the project completion date. By experimenting
with different logical sequences and /or durations the optimal
project schedule can be determined.
Critical Performance Indicator
A critical factor against which aspects of
project performance may be assessed
Critical Success Factor
A factor considered to be most conducive to
the achievement of a successful project
Customer
Any person, who defines needs or wants,
justifies or pays for part or the entire project, or evaluates
or uses the results. Could be the project promoter, client,
owner or employer
Cut-off Date
The ending date of a reporting period.
Top of Page
Dangle
An activity or network which has either no
predecessors or no successors. If neither, it is referred to as
an isolated activity.
Decision Event
State in the progress of a project when a
decision is required before the start of any succeeding
activity. Note The decision determines which of a number of
alternative paths is to be followed.
Delaying Resource
In resource scheduling, inadequate
availability of one or more resources may require that the
completion of an activity be delayed beyond the date on which it
could otherwise be completed. The delaying resource is the first
resource on an activity that causes the activity to be delayed.
Delegation
The practice of getting others to perform
work effectively which one chooses not to do oneself. The
process by which authority and responsibility is distributed
from Project Manager to subordinates.
Deliberate Decision Event
Decision event where the decision is made
as a result of the outcomes of the preceding activities and
possibly other information but it cannot be made automatically
Deliverables
End products of a project or the measurable
results of intermediate activities within the project
organization Note: Deliverables may be in the form of hardware,
software, services, processes, documents or any combination
thereof.
Delphi Technique
A process where a consensus view is reached
by consultation with experts. Often used as an estimating
technique.
Dependency
Precedence relationship. Restriction that
one activity has to precede, either in part or in total, another
activity. Dependencies are relationships between
products or tasks. For example, one product may be made up of
several other ‘dependent’ products or a task may not begin
until a ‘dependent’ task is complete. See also logical
relationship.
Dependency Arrow
A link arrow used in an activity on node
network to represent the interrelationships of activities in a
project
Design Authority
The person or organization with overall
design responsibility for the products of the project
Design and Development Phase
The time period in which production process
and facility and production processes are developed and
designed.
Deterministic Network
Network containing paths, all of which have
to be followed and whose durations are fixed. Note:
Deterministic network is a term used to distinguish traditional
networking from probabilistic networking
Direct Costs
Costs that are specifically attributable to
an activity or group of activities without apportionment.
(Direct costs are best contrasted with indirect costs that
cannot be identified to a specific project.)
Discounted Cash Flow (DCF)
Concept of relating future cash inflows and
outflows over the life of a project or operation to a common
base value thereby allowing more validity to comparison of
projects with different durations and rates of cash flow.
Discrete Milestone
A milestone that has a definite scheduled
occurrence in time. Logical link that may require time but
no other resource.
Dummy activity in activity on arrow
network
An activity representing no actual work to
be done but required for reasons of logic or nomenclature. Note:
There are three uses for a dummy activity in 'activity-on-arrow
network' a) logic, b) time delay and c) uniqueness.
Duration
Duration is the length of time needed to
complete an activity.
Duration Compression
Often resulting in an increase in cost,
duration compression is the shortening of a project schedule
without reducing the project scope.
Top of Page
Earliest Feasible Date
The earliest date on which the activity
could be scheduled to start based on the scheduled dates of all
its predecessors, but in the absence of any resource constraints
on the activity itself. This date is calculated by resource
scheduling.
Early Dates
Calculated in the forward pass of time
analysis, early dates are the earliest dates on which an
activity can start and finish.
Early Finish
Earliest Finish Time*
Earliest Finish Time
Earliest possible time by which an activity
can finish within the logical and imposed constraints of the
network. (The Early Finish date is defined as the earliest
calculated date on which an activity can end. It is based on the
activity's Early Start which depends on the finish of
predecessor activities and the activity's duration)
Early Start Time
Earliest possible time by which an activity
can start within the logical and imposed constraints of the
network.
Earned Hours
The time in standard hours credited as a
result of the completion of a given task or a group of tasks.
Earned Value
The value of the useful work done at any
given point in a project. Note: The budget may be
expressed in cost or labor hours.
Earned Value Analysis
Analysis of project progress where the
actual money, hours (or other measure) budgeted and spent is
compared to the value of the work achieved.
Earned Value Cost Control
The quantification of the overall progress
of a project in financial terms so as to provide a realistic
yardstick against which to compare the actual cost to date.
Earned Value Management
Earned Value Analysis
Earned Value Analysis
Technique for assessing whether the earned
value in relation to the amount of work completed, is ahead, on,
or behind plan.
Effort
The number of labor units necessary to
complete the work. Effort is usually expressed in staff-hours,
staff-days or staff-weeks and should not be confused with
duration.
Effort-Driven Activity
An activity whose duration is governed by
resource usage and availability. The resource requiring the
greatest time to complete the specified amount of work on the
activity will determine its duration.
Effort Remaining
The estimate of effort remaining to
complete an activity.
Elapsed Time
Elapsed time is the total number of
calendar days (excluding non-work days such as weekends or
holidays) that is needed to complete an activity. It gives a
realistic view of how long an activity is scheduled to take for
completion.
End Activity
An activity with no logical successors.
End Event (of a project)
Event with preceding, but no succeeding
activities. Note: There may be more than one end event.
Environmental Factoring
Use of data relating to an external factor
(such as the weather) to modify or bias the value of parameters
concerned.
Equivalent Activity
Activity that is equivalent, in the
probabilistic sense, to any combination of series and parallel
activities.
Estimate
A quantified assessment of the resources
required to complete part or all of a project. The prediction of
the quantitative result. It is usually applied to project costs,
resources and durations.
Estimate At Completion (EAC)
A value expressed in either money and /or
hours, to represent the projected final costs of work when
completed. The EAC is calculated as ETC + ACWP.
Estimate To Complete (ETC)
The value expressed in either money or
hours developed to represent the cost of the work required to
complete a task.
Estimating
The act of combining the results of post
project reviews, metrics, consultation and informed assessment
to arrive at time and resource requirements for an activity.
Event
State in the progress of a project after
the completion of all preceding activities, but before the start
of any succeeding activity. (A defined point that is the
beginning or end of an activity)
Exception Report
Focused report drawing attention to
instances where planned and actual results are expected to be,
or are already, significantly different. Note: An exception
report is usually triggered when actual values are expected to
cross a predetermined threshold that is set with reference to
the project plan The actual values may be trending better or
worse than plan.
Exclusive OR Relationship
Logical relationship indicating that only
one of the possible activities can be undertaken.
Execution phase
The phase of a project in which work
towards direct achievement of the project’s objectives and the
production of the project’s deliverables occurs. Sometimes
called the implementation phase
Expenditure
A charge against available funds, evidenced
by a voucher, claim, or other documents. Expenditures represent
the actual payment of funds.
Exceptions
Exceptions are occurrences that cause
deviation from a plan, such as issues, change requests and
risks. Exceptions can also refer to items where the cost
variance and schedule variance exceed predefined thresholds.
External Constraint
A constraint from outside the project
network.
Top of Page
Fast–Tracking
Reducing the duration of a project usually
by overlapping phases or activities that were originally planned
to be done sequentially. (The process of reducing the
number of sequential relationships and replacing them typically
with parallel relationships (usually to achieve shorter overall
durations but often with increased risk)).
Fallback Plan
A plan for an alternative course of action
that can be adopted to overcome the consequences of a risk,
should it occur (including carrying out any advance activities
that may be required to render the plan practical)
Feasibility Phase
The project phase that demonstrates that
the client's requirement can be achieved and identifies and
evaluates the options to determine the one preferred solution
Feasibility Study
Analysis to determine if a course of action
is possible within the terms of reference of the project.
Feasible schedule
Any schedule capable of implementation
within the externally determined constraints of time and/or
resource limits.
Final Report
Post-implementation report. Normally a
retrospective report that formally closes the project having
handed over the project deliverables for operational use Note:
The report should draw attention to experiences that may be of
benefit to future projects and may form part of the
accountability of the project team
Finish Date
The actual or estimated time associated
with an activity’s completion.
Finishing Activity
A finishing activity is the last activity
that must be completed before a project can be considered
finished. This activity is not a predecessor to any other
activity -- it has no successors.
Finish-To-Finish Lag
The finish-to-finish lag is the minimum
amount of time that must pass between the finish of one activity
and the finish of its successor(s)
Finish-To-Start Lag
The finish-to-start lag is the minimum
amount of time that must pass between the finish of one activity
and the start of its successor(s). The default finish-to-start
lag is zero.
Firm Fixed Price Contract
A contract where the buyer pays a set
amount to the seller regardless of that seller’s cost to
complete the contract.
Fixed Date
A calendar date (associated with a plan)
that cannot be moved or changed during the schedule.
Fixed-Duration Scheduling
A scheduling method in which, regardless of
the number of resources assigned to the task, the duration
remains the same.
Fixed Finish
See Imposed Finish.
Fixed Price Contracts
A generic category of contracts based on
the establishment of firm legal commitments to complete the
required work. A performing contractor is legally obligated to
finish the job, no matter how much it costs to complete. Risks
of all cost growth rest on the performing contractor.
Fixed Start
See Imposed Start.
Float
Time available for an activity or path in
addition to its planned duration. (Float is the amount of
time that an activity can slip past its earliest completion date
without delaying the rest of the project. The calculation
depends on the float type. See start float, finish float, free
float, positive float, and negative float)
Forecast At Completion
Scheduled cost for a task.
Forecast Final Cost
See Estimate at Completion.
Forward Pass
A procedure whereby the earliest event
times or the earliest start and finish times for the activities
of a network are calculated.
Free Float
Time by which an activity may be delayed or
extended without affecting the start of any succeeding activity.
Note: free float can never be negative.
Functional Organization
Management structure where specific
functions of an organization are grouped into specialist
departments providing dedicated services. Note: Examples of
functional organization are finance, marketing and design
departments.
Functional Specification
A document specifying in some detail the
functions that are required of a system and the constraints that
will apply
Functional Manager
The person responsible for the business and
technical management of a functional group.
Functional Matrix
An organization type where the project has
a team leader in each functional department and the products are
passed from one team to the next.
Functional Organization
A functional management structure where
specific functions of a business are grouped into specialist
departments that provide a dedicated service to the whole of the
organization e.g. accounts department, production department,
drawing office.
Funding Profile
An estimate of funding requirements over
time.
Top of Page
Gantt Chart
Particular type of bar chart showing
planned activity against time. Note: 'Gantt Chart',
although named for a particular type of bar chart, is in current
usage as a name for bar charts in general. (A Gantt chart is a
time-phased graphic display of activity durations. Activities
are listed with other tabular information on the left side with
time intervals over the bars. Activity durations are shown in
the form of horizontal bars.)
Goal
A one-sentence definition of specifically
what will be accomplished, while incorporating an event
signifying completion.
Top of Page
Hammock
Activity, joining two specified points,
that span two or more activities. Note: Its duration is
initially unspecified and is only determined by the durations of
the specified activities. Note: Hammocks are usually used to
collect time-dependent information, e.g. overheads. (A group of
activities, milestones, or other hammocks aggregated together
for analysis or reporting purposes. Sometimes used to describe
an activity such as management support that has no duration of
its own but derives one from the time difference between the two
points to which it is connected)
Hand-over
The formal process of transferring
responsibility for and ownership of the products of a project to
the operator or owner
Hierarchical Coding Structure
A coding system that can be represented as
a multi-level tree structure in which every code except those at
the top of the tree has a parent code.
Hierarchy of Networks
Range of networks at different levels of
detail, from summary down to working levels, showing the
relationships between those networks
Histogram
A graphic display of planned and or actual
resource usage over a period of time. It is in the form of a
vertical bar chart, the height of each bar representing the
quantity of resource usage in a given time unit. Bars may be
single, multiple or show stacked resources.
Holiday
An otherwise valid working day that has
been designated as exempt from work.
Host Organization
Organization that provides the
administrative and logistical support for the project.
Hypercritical Activities
Activities on the critical path with
negative float.
Top of Page
Impact
The assessment of the adverse effects of an
occurring risk.
Impact Analysis
Assessing the merits of pursuing a
particular course of action.
Implementation Phase
The project phase that develops the chosen
solution into a completed deliverable. (Note: Realization is the
internationally accepted and preferred term for implementation)
Imposed Date
Point in time determined by circumstances
outside the network. Note: A symbol is inserted immediately
above the event concerned on activity on arrow networks or
adjacent and connected to the appropriate corner of the node on
activity on node networks
Imposed Finish
A finished date imposed on an activity by
external constraints.
Imposed Start
A start date imposed on an activity by
external constraints.
Inclusive OR relationship
Logical relationship indicating that at
least one but not necessarily all of the activities have to be
undertaken
INCOTERMS
A set of international terms defining
conditions for delivery and shipping of equipment and materials
Incurred Costs
Sum of actual and committed costs, whether
invoiced/paid or not, at a specified time
Indirect Cost
Costs associated with a project that cannot
be directly attributed to an activity or group of activities.
(Resources expended which are not directly identified to any
specific contract, project, product or service, such as
overheads and general administration)
In-house Project
A project commissioned and carried out
entirely within a single organization
Initiation
Committing the organization to begin a
project.
In Progress
An activity that has been started, but not
yet completed.
Integrated Logistics Support
Disciplined approach to activities
necessary to a) cause support considerations to be
integrated into product design b) develop support
arrangements that are consistently related to design and to each
other and c) provide the necessary support at the
beginning and during customer use at optimum cost.
Integration
The process of bringing people, activities
and other things together to perform effectively.
Internal Rate of Return (IRR)
Discount rate at which the net present
value of a future cash flow is zero. Note: IRR is a special case
of the ‘discounted cash flow’ procedures.
Inverted Matrix
A project oriented organization structure
that employs permanent specialists to support projects
Issue
An immediate problem requiring resolution
Top of Page
Key Events
Major events the achievement of which that
are deemed to be critical to the execution of the project
Key Performance Indicators
Measurable indicators that will be used to
report progress that is chosen to reflect the critical success
factors of the project.
Top of Page
Labor Rate Variances
Difference between planned labor rates and
actual labor rates.
Ladder
Device for representing a set of
overlapping activities in a network diagram. Note: The start and
finish of each succeeding activity are linked only to the start
and finish of the preceding activity by lead and lag activities,
which consume only time.
Lag
a) In a network diagram, the minimum
necessary lapse of time between the finish of one activity and
the finish of an overlapping activity b) delay incurred between
two specified activities
Late Dates
Calculated in the backward pass of time
analysis, late dates are the latest dates by which an activity
can be allowed to start or finish.
Latest Event Time
Latest time by which an event has to occur
within the logical and imposed constraints of the network,
without affecting the total project duration
Late Event Date
Calculated from backward pass, it is the
latest date an event can occur.
Latest Finish Time
The latest possible time by which an
activity has to finish within the logical activity and imposed
constraints of the network, without affecting the total project
duration
Latest Start Time
Latest possible time by which an activity
has to start within the logical and imposed constraints of the
network, without affecting the total project duration
Lead
In a network diagram, the minimum necessary
lapse of time between the start of one activity and the start of
an overlapping activity
Lead Contractor
The contractor who has responsibility for
overall project management and quality assurance
Leadership
Getting others to follow
Letter of Intent
A letter indicating an intent to sign a
contract, usually so that work can commence prior to signing
that contract.
Leveling
See Resource Leveling.
Life Cycle
A sequence of defined stages over the full
duration of a project
Life-Cycle Costing
When evaluating alternatives, Life-Cycle
Costing is the concept of including acquisition, operating and
disposal costs.
Likelihood
Assessment of the probability that a risk
will occur.
Line Manager
The manager of any group that makes a
product or performs a service.
Linked Bar Chart
A bar chart that shows the dependency links
between activities
Logic
See Network Logic.
Logic Diagram
A diagram that displays the logical
relationships between project activities
Logical Relationship
A logical relationship is based on the
dependency between two project activities or between a project
activity and a milestone.
Loop
An error in a network which results in a
later activity imposing a logical restraint on an earlier
activity
Top of Page
Management by Project
A term used to describe normal management
processes that are being project managed.
Management Development
All aspects of staff planning, recruitment,
development, training and assessment.
Management Reserve
A central contingency pool. Sum of money
held as an overall contingency to cover the cost impact of some
unexpected event occurring. Note: This is self-insurance
Master Network
Network showing the complete project, from
which more detailed networks are derived
Master Schedule
A high level summary project schedule that
identifies major activities and milestones.
Material
Property which may be incorporated into or
attached to an end item to be delivered under a contract or
which may be consumed or expended in the performance of a
contract. It includes, but is not limited to raw and processed
material, parts, components, assemblies, fuels and lubricants,
and small tools and supplies which may be consumed in normal use
in the performance of a contract.
Matrix Organization
An organizational structure where the
Project Manager and the Functional Managers share the
responsibility of assigning priorities and for directing the
work.
Methodology
A documented process for management of
projects that contains procedures, definitions and roles and
responsibilities.
Mid-Stage Assessment
An assessment in the middle of a project
that can be held for several reasons: 1) at the request of
the project board; 2) to authorize work on the next stage before
current one is completed; 3) to allow for a formal review in the
middle of a long project; or 4) to review exception plans.
Milestone
A key event. An event selected for its
importance in the project. Note: Milestones are commonly used in
relation to progress. (A milestone is often chosen to represent
the start of a new phase or completion of a major deliverable.
They are used to monitor progress at summary level. Milestones
are activities of zero duration)
Milestone Plan
A plan containing only milestones which
highlight key points of the project.
Milestone Schedule
A schedule that identifies the major
milestones. See also Master Schedule.
Mission Statement
Brief summary, approximately one or two
sentences, that sums up the background, purposes and benefits of
the project.
Mitigation
Working to reduce risk by lowering its
chances of occurring or by reducing its effect if it occurs.
Mobilization
The bringing together of project personnel
and securing equipment and facilities. Carried out during
project start-up phases
Monitoring
Monitoring is the recording, analyzing and
reporting of project performance as compared to the plan.
Monte Carlo Simulation
A technique used to estimate the likely
range of outcomes from a complex process by simulating the
process under randomly selected conditions a large number of
times.
Multi-Project
A project consisting of multiple
subprojects.
Multi-Project Analysis
Multi-project analysis is used to analyze
the impact and interaction of activities and resources whose
progress affects the progress of a group of projects or for
projects with shared resources or both. Multi-project analysis
can also be used for composite reporting on projects having no
dependencies or resources in common.
Multi-Project Management
Managing multiple projects that are
interconnected either logically or by shared resources.
Multi-project Scheduling
Use of the techniques of resource
allocation to schedule more than one project concurrently
Top of Page
Near-Critical Activity
A low total float activity.
Negative Total Float
Time by which the duration of an activity
or path has to be reduced in order to permit a limiting imposed
date to be achieved
Negotiated Contract Cost
The estimated cost negotiated in a
Cost-Plus-Fixed-Fee Contract or the negotiated contract target
cost in either a Fixed Price-Incentive Contract or a
Cost-Plus-Incentive-Fee Contract. See also Contract Target Cost.
Negotiation
The art of satisfying needs by reaching
agreement or compromise with other parties.
Net Present Value
Aggregate of future net cash flows
discounted back to a common base date, usually the present
Network
A pictorial presentation of project data in
which the project logic is the main determinant of the
placements of the activities in the drawing. Frequently called a
flowchart, PERT chart, logic drawing, or logic diagram.
Network Analysis
Method used for calculating a project's
critical path and activity times and floats. Note: See also
critical path analysis, project network techniques.
Network Interface
Activity or event common to two or more
network diagrams
Network Logic
The collection of activity dependencies
that make up a project network.
Network Path
A series of connected activities in a
project network.
Nodes
Points in a network at which arrows start
and finish
Non-recurring Costs
Expenditures against specific tasks that
are expected to occur only once on a given project.
Non-splittable Activity
An activity that, once started, has to be
completed to plan without interruption. Note: Resources should
not be diverted from a non-splittable activity to another
activity
Not Earlier Than
A restriction on an activity that indicates
that it may not start or end earlier than a specified date.
Not Later Than
A restriction on an activity that indicates
that it may not start or end later than a specified date.
Top of Page
Objectives
Predetermined results toward which effort
is directed.
Operation Phase
Period when the completed deliverable is
used and maintained in service for its intended purpose
Opportunity
The opposite of a risk. The chance to
enhance the project benefits
Order of Magnitude Estimate
An estimate carried out to give very
approximate indication of likely out-turn costs.
Organization Design
The design of the most appropriate
organizational design for a project.
Organizational Breakdown Structure
(OBS)
Hierarchical way in which the organization
may be divided into management levels and groups, for planning
and control purposes
Organizational Planning
The process of identifying, assigning and
documenting project responsibilities and relationships.
Original Budget
The initial budget established at or near
the time a contract was signed or a project authorized, based on
the negotiated contract cost or management’s authorization.
Original Duration
The duration of activities or groups of
activities as recorded in the Baseline Schedule.
Other Direct Costs (ODC)
A group of accounting elements which can be
isolated to specific tasks, other than labor and material.
Included in ODC are such items as travel, computer time, and
services.
Out-of-Sequence Progress
Progress that has been reported even though
activities that have been deemed predecessors in project logic
have not been completed.
Output Format
Information that governs the final
appearance of a report or drawing. (Usually refers to
computer–generated documents)
Outsourcing
Contracting-out, buying in facilities or
work (as opposed to using in-house resources).
Overall Change Control
Co-coordinating and controlling changes
across an entire project
Overhead
Costs incurred in the operation of a
business that cannot be directly related to the individual
products or services being produced. See also "Indirect
Cost."
Overrun
Costs incurred in excess of the contract
target costs on an incentive type contract or the estimated
costs on a fixed fee contract. An overrun is that value of costs
which are needed to complete a project, over that value
originally authorized by management.
Top of Page
Parallel Activities
Parallel activities are two or more
activities than can be done at the same time. This allows a
project to be completed faster than if the activities were
arranged serially.
Parent Activity
Task within the work breakdown structure
that embodies several subordinate 'child' tasks
Parties (to a contract)
The persons or companies who sign a
contract with one another
Path
Activity or an unbroken sequence of
activities in a project network (Refer to critical path
method for information on critical and non-critical paths).
Percent Complete
A measure of the completion status of a
partially completed activity. May be aggregated to sections of a
project or the whole project
Performance Measurement Techniques
Performance measurement techniques are the
methods used to estimate earned value. Different methods are
appropriate to different work packages, either due to the nature
of the work or to the planned duration of the work package.
Performance Specification
Statement of the totality of needs
expressed by the benefits, features, characteristics, process
conditions, boundaries and constraints that together define the
expected performance of a deliverable. Note: A performance
specification should provide for innovation and alternative
solutions, by not defining or unduly constraining the technical
attributes of the intended deliverable
Performing
A team building stage where the emphasis is
on the work currently being performed.
Phase (of a project)
That part of a project during which a set
of related and interlinked activities are performed. Note: A
project consists of a series of phases that together constitute
the whole project life cycle
Physical Percent Complete
The percentage of the work content of an
activity that has been achieved.
Pilot
A form of testing a new development and its
implementation prior to committing to its full release
Plan
A plan is an intended future course of
action. It is owned by the project manager, it is the basis of
the project controls and includes the ‘what’, the ‘how’,
the ‘when’, and the ‘who’
Planned Activity
An activity not yet started.
Planned Cost
Estimated cost of achieving a specified
objective
Planning
The process of identifying the means,
resources and actions necessary to accomplish an objective.
Planning Stage
The stage prior to the implementation stage
when product activity, resource and quality plans are produced.
Planner
A member of a project team or project
support office with the responsibility for planning, scheduling
and tracking of projects. They are often primarily concerned
with schedule, progress and manpower resources.
Portfolio
A grouping or bundle of projects, collected
together for management convenience. They may or may not have a
common objective; they are often related only by the use of
common resources
Portfolio Management
The management of a number of projects that
do not share a common objective
Positive Float
Positive float is defined as the amount of
time that an activity's start can be delayed without affecting
the project completion date. An activity with positive float is
not on the critical path and is called a non-critical activity.
The difference between early and late dates (start or finish)
determines the amount of float.
Post Implementation Review
A review between 6-12 months after a system
in a project has met its objectives to verify that it continues
to meet user requirements.
Post Project Appraisal
An evaluation that provides feedback in
order to learn for the future.
Precedence Diagram Method
One of the two methods of representing
project as networks, in which the activities are represented by
nodes and the relationships between them by arrows
Precedence Network
A multiple dependency network. An
activity-on-node network in which a sequence arrow represents
one of four forms of precedence relationship, depending on the
positioning of the head and the tail of the sequence arrow. The
relationships are: a) Start of activity depends on finish of
preceding activity, either immediately or after a lapse of time
b) Finish of activity depends on finish of preceding activity,
either immediately or after a lapse of time c) Start of activity
depends on start of preceding activity, either immediately or
after a lapse of time d) Finish of activity depends on start of
preceding activity, either immediately or after a lapse of time.
Preceding Event
In an activity-on-arrow network, an event
at the beginning of an activity
Pre- commissioning
That work which is carried out prior to
commissioning in order to demonstrate that commissioning may be
safely undertaken
Predecessor
An activity that must be completed (or be
partially completed) before a specified activity can begin
Predecessor Activity
In the precedence diagramming method this
is an activity which logically precedes the current activity.
Prime or Lead Contractor
A main supplier who has a contract for much
or all of the work on a contract
Probabilistic Network
Network containing alternative paths with
which probabilities are associated
Probability
Likelihood of a risk occurring.
Process
Set of interrelated resources and
activities which transform inputs into outputs
Procurement
The securing of goods or services
Procurement Planning
Determining what to procure and when.
Product Breakdown Structure
A hierarchy of deliverable products which
are required to be produced on the project. It forms the base
document from which the execution strategy and product-based
work breakdown structure may be derived. It provides a guide for
Configuration Control documentation
Product Description
The description of the purpose form and
components of a product. It should always be used as a basis for
acceptance of the product by the customer.
Product Flow Diagram
Represents how the products are produced by
identifying their derivation and the dependencies between them.
Program
A broad effort encompassing a number of
projects and/or functional activities with a common purpose.
Program Benefits Review
A review to assess if targets have been
reached and to measure the performance levels in the resulting
business operations.
Program Director
The senior manager with the responsibility
for the overall success of the program.
Program Directorate
A committee that directs the program when
circumstances arise where there is no individual to direct the
program.
Program Evaluation and Review
Technique (PERT)
PERT is a project management technique for
determining how much time a project needs before it is
completed. Each activity is assigned a best, worst, and most
probable completion time estimate. These estimates are used to
determine the average completion time. The average times are
used to calculate the critical path and the standard deviation
of completion times for the entire project.
Program Management
The effective management of several
individual but related projects or functional activities in
order to produce an overall system that works effectively.
Program Management Office
The office responsible for the business and
technical management of a specific contract or program.
Program Manager
Individual or body with responsibility for
managing a group of projects
Program Support Office
A group that gives administrative support
to the program manager and the program executive.
Progress
The partial completion of a project, or a
measure of the same.
Progress Payments
Payments made to a contractor during the
life of a fixed-price type contract, on the basis of some
agreed-to formula, for example, Budget Cost of Work Performed or
simply costs incurred.
Progress Report
A regular report to senior personnel,
sponsors or stakeholders summarizing the progress of a project
including key events, milestones, costs and other issues.
Project
Unique set of co-coordinated activities,
with definite starting and finishing points, undertaken by an
individual or organization to meet specific objectives within
defined time, cost and performance parameters (See also BS ISO
10006.) (Alternative definition: An Endeavour in which
human, material and financial resources are organized in a novel
way to deliver a unique scope of work of given specification,
often within constraints of cost and time, and to achieve
beneficial change defined by quantitative and qualitative
objectives.)
Project Appraisal
The discipline of calculating the viability
of a project.
Project Base Date
Reference date used as a basis for the
start of a project calendar
Project Board
A project board is the body to which the
Project Manager is accountable for achieving the project
objectives
Project Brief
Statement that describes the purpose, cost,
time and performance requirements/constraints for a project (A
statement of reference terms for a project. A written statement
of the Client’s goals and requirements in relation to the
project)
Project Calendar
A calendar that defines global project
working and non-working periods.
Project Coordination
Communication linking various areas of a
project to ensure the transfer of information or hardware at
interface points at the appropriate times and identification of
any further necessary resources
Project Coordination Procedure
Defines the parties relevant to the project
and the approved means of communicating between them
Project Champion
Person within the parent organization who
promotes and defends a project
Project Closure
Formal termination of a project at any
point during its life.
Project Cost Management
A subset of project management that
includes resource planning, cost estimating, cost control and
cost budgeting in an effort to complete the project within its
approved budget.
Project Culture
The general attitude toward projects within
the business.
Project Definition
A report that defines a project i.e. why it
is required, what will be done, how when and where it will be
delivered, the organization and resources required, the
standards and procedures to be followed.
Project Director
The manager of a very large project that
demands senior level responsibility or the person at the board
level in an organization who has the overall responsibility for
projects management.
Project Environment
The project environment is the context
within which the project is formulated, assessed and realized.
This includes all external factors that have an impact on the
project.
Project Evaluation
A documented review of the project’s
performance, produced at project closure. It ensures that the
experience of the project is recorded for the benefit of others.
Project File
A file containing the overall plans of a
project and any other important documents.
Project Initiation
The beginning of a project at which point
certain management activities are required to ensure that the
project is established with clear reference terms and adequate
management structure.
Project Initiation Document
A document approved by the project board at
project initiation that defines the terms of reference for the
project.
Project Issue Report
A report that raises either technical or
managerial issues in a project.
Project Life-Cycle
All phases or stages between a project's
conception and its termination. Note: The project life cycle may
include the operation and disposal of project deliverables. This
is usually known as an 'extended life cycle'
Project Life Cycle Cost
Cumulative cost of a project over its whole
life cycle
Project Log
A project diary. A chronological record of
significant occurrences throughout the project
Project Logic
The relationships between the various
activities in a project.
Project Logic Drawing
A representation of the logical
relationships of a project.
Project Management
Planning, monitoring and control of all
aspects of a project and the motivation of all those involved in
it to achieve the project objectives on time and to the
specified cost, quality and performance (Alternative definition
- The controlled implementation of defined change).
Project Management Body of Knowledge
This is an inclusive term that describes
the sum of knowledge within the profession of project
management. As with other professions, such as law and medicine,
the body of knowledge rests with the practitioners and academics
that apply and advance it.
Project Management Plan
A plan for carrying out a project, to meet
specific objectives, that is prepared by or for the project
manager
Project Management Software
Computer application software designed to
help with planning and controlling resources, costs and
schedules of a project. It may also provide facilities for
documentation management, risk analysis etc.
Project Management Team
Members of the project team who are
directly involved in its management.
Project Manager
Individual or body with authority,
accountability and responsibility for managing a project to
achieve specific objectives
Project Matrix
An organization matrix that is project
based in which the functional structures are duplicated in each
project.
Project Monitoring
Comparison of current project status with
what was planned to be done to identify and report any
deviations
Project Network
Representation of activities and/or events
with their inter- relationships and dependencies
Project Network Techniques
Group of techniques that, for the
description, analysis, planning and control of projects,
considers the logical inter relationships of all project
activities The group includes techniques concerned with time,
resources, costs and other influencing factors, e.g.
uncertainty. Note: The terms ‘program evaluation and review
technique’ (PERT) 'critical path analysis' (CPA), 'critical
path method' (CPM) and 'precedence method' refer to particular
techniques and should not be used as synonyms for project
network
Project Organization
Structure that is created or evolves to
serve the project and its participants (A term which refers
to the structure, roles and responsibilities of the project team
and its interfaces to the outside world.)
Project Phase
A group of related project activities that
come together with the completion of a deliverable.
Project Plan
A document for management purposes that
gives the basics of a project in terms of its objectives,
justification, and how the objectives are to be achieved. This
document is used as a record of decisions and a means of
communication among stakeholders. It gives the supporting detail
to the project definition which details the schedule, resource
and costs for the project.
Project Planning
Developing and maintaining a project plan.
Project Portfolio
The constituent projects within a program.
Project Procedures Manual
A collected set of the management and
administrative procedures needed for the project
Project Procurement Management
A subset of project management that
includes procurement planning, source selection, enquiry, tender
assessment, placement of purchase orders and contracts for goods
and services, contract and purchase order administration and
close-out in an effort to obtain goods and services from outside
organizations.
Project Progress Report
Formal statement that compares the project
progress, achievements and expectations with the project plan.
Project Quality Management
A subset of project management that
includes quality planning, quality assurance and quality control
to satisfy the needs and purpose of the project.
Project Review Calendar
Calendar of project review dates, meetings
and issues of reports set against project week numbers or dates
Project Risk Management
A subset of project management that
includes risk identification, risk quantification, risk response
development and risk response control in an effort to identify,
analyze and respond to project risks.
Project Schedule
Project program (Planned dates for starting
and completing activities and milestones)
Project Scope Management
A subset of project management that
includes initiation, scope planning, scope definition, scope
verification and scope change control in an effort to ensure
that the project has all of the necessary work required to
complete it.
Project Sponsor
(1) The individual or body for whom the
project is undertaken, the primary risk taker (2) The individual
representing the sponsoring body and to whom the project manager
reports (3) A person or organization providing funds for the
project.
Project Start-up
The creation of the project team
Project Status Report
A report on the status of accomplishments
and any variances to spending and schedule plans.
Project Strategy
A comprehensive definition of how a project
will be developed and managed.
Project Success/Failure Criteria
The criteria by which the success or
failure of a project may be judged.
Project Support Office
The central location of planning and
project support functions. Often provides personnel and
facilities for centralized planning, cost management,
estimating, documentation control and sometimes procurement to a
number of projects.
Project Team
Set of individuals, groups and/or
organizations that are responsible to the project manager for
undertaking project tasks (Includes all contractors and
consultants)
Project Technical Plan
A plan produced at the beginning of a
project that addresses technical issues and strategic issues
related to quality control and configuration management.
Project Time Management
A subset of project management that
includes activity definition, activity sequencing, activity
duration estimating, schedule development and schedule control
in order to complete the project on time.
Public Relations
An activity meant to improve the project
organization's environment in order to improve project
performance and reception.
Top of Page
Qualitative Risk Analysis
A generic term for subjective methods of
assessing risks.
Quality
A trait or characteristic used to measure
the degree of excellence of a product or service. Meeting
customer’s needs.
Quality Assurance (QA)
The process of evaluating overall project
performance on a regular basis to provide confidence that the
project will satisfy the relevant quality standards.
Quality Assurance Plan
A plan that guarantees a quality approach
and conformance to all customer requirements for all activities
in a project.
Quality Audit
An official examination to determine
whether practices conform to specified standards or a critical
analysis of whether a deliverable meets quality criteria
Quality Control (QC)
The process of monitoring specific project
results to determine if they comply with relevant standards and
identifying ways to eliminate causes of unsatisfactory
performance.
Quality Criteria
The characteristics of a product that
determines whether it meets certain requirements.
Quality Guide
The quality guide describes quality and
configuration management procedures and is aimed at people
directly involved with quality reviews, configuration management
and technical exceptions.
Quality Plan (for a project)
That part of the project plan that concerns
quality management and quality assurance strategies (see also
ISO 10006)
Quality Planning
Determining which quality standards are
necessary and how to apply them.
Quality Review
A review of a product against an
established set of quality criteria.
Top of Page
Recurring Costs
Expenditures against specific tasks that
would occur on a repetitive basis. Examples are the hire of
computer equipment, tool maintenance, etc.
Relationship
A logical connection between two
activities.
Remaining Duration
Time needed to complete the remainder of an
activity or project.
Re-planning
Actions performed for any remaining effort
within project scope. Often the cost and/or schedule variances
are zeroed out at this time for history items.
Request for Change
A proposal by the project manager for a
change to the project as a result of a project issue report.
Request for Proposal
A bid document used to request proposals
from prospective sellers of products or services.
Request for Quotation
Equivalent to a Request for Proposal but
with more specific application areas.
Requirements
A negotiated set of measurable customer
wants and needs.
Requirements Definition
Statement of the needs that a project has
to satisfy
Resource
Any variable capable of definition that is
required for the completion of an activity and may constrain the
project. Note 1: A resource may be non-storable so that its
availability has to be renewed for each time period (even if it
was not utilized in previous time periods). Note 2: A resource
may be storable so that it remains available unless depleted by
usage. Such a resource may also be replenished by activities
producing credited and storable resource. (Resources can be
people, equipment, facilities, funding or anything else needed
to perform the work of a project).
Resource Aggregation
Summation of the requirements for each
resource, and for each time period. Note: Where the
earliest start time of an activity is used alone, it is often
termed an ‘early start’ aggregation. Similarly a ‘late
start’ aggregation uses the latest start times.
Resource Allocation
Scheduling of activities and the resources
required by those activities, so that predetermined constraints
of resource availability and/or project time are not exceeded
Resource Analysis
The process of analyzing and optimizing the
use of resources on a project. Often uses resource leveling and
resource smoothing techniques.
Resource Assignment
The work on an activity related to a
specific resource.
Resource Availability
The level of availability of a resource,
which may vary over time.
Resource Breakdown Structure
A hierarchical structure of resources that
enables scheduling at the detailed requirements level, and roll
up of both requirements and availabilities to a higher level.
Resource Calendar
A calendar that defines the working and
non-working patterns for specific resources.
Resource Constraint
Limitation due to the availability of a
resource.
Resource Accumulation
Process of accumulating the requirements
for each resource to give the total required to date at all
times throughout the project.
Resource Driven Task Durations
Task durations that are driven by the need
for scarce resources.
Resource Histogram
A view of project data in which resource
requirements, usage, and availability are shown using vertical
bars against a horizontal time scale.
Resource Level
A specified level of resource units
required by an activity per time unit.
Resource Leveling
See resource limited scheduling.
Resource Limited Scheduling
Scheduling of activities, so that
predetermined resource levels are never exceeded. Note: This may
cause the minimum overall or specified project duration to be
exceeded
Resource Optimization
A term for resource leveling and resource
smoothing.
Resource Plan
Part of the definition statement stating
how the program will be resource loaded and what supporting
services, infrastructure and third party services are required.
Resource Planning
Evaluating what resources are needed to
complete a project and determining the quantity needed.
Resource Requirement
The requirement for a particular resource
by a particular activity.
Resource Scheduling
The process of determining dates on which
activities should be performed in order to smooth the demand for
resources, or to avoid exceeding stated constraints on these
restraints.
Resource Smoothing
Scheduling of activities, within the limits
of their float, so that fluctuations in individual resource
requirements are minimized. (In smoothing, as opposed to
resource leveling, the project completion date may not be
delayed)
Responsibility Matrix
A document correlating the work required by
a Work Breakdown Structure element to the functional
organizations responsible for accomplishing the assigned tasks.
Responsible Organization
A defined unit within the organization
structure which is assigned responsibility for accomplishing
specific tasks, or cost accounts.
Retention
A part of payment withheld until the
project is completed in order to ensure satisfactory performance
or completion of contract terms.
Revenue Cost
Expenditure charged to the profit and loss
account as incurred or accrued due
Risk
Combination of the probability or frequency
of occurrence of a defined threat or opportunity and the
magnitude of the consequences of the occurrence. Note:
Combination of the likelihood of occurrence of a specified event
and its consequences (Potential occurrences or threats that
would jeopardize the success of a project. The probability of an
undesirable outcome.)
Risk Analysis
Systematic use of available information to
determine how often specified events may occur and the magnitude
of their likely consequences. (A technique designed to quantify
the impact of uncertainty)
Risk Assessment
The process of identifying potential risks,
quantifying their likelihood of occurrence and assessing their
likely impact on the project
Risk Avoidance
Planning activities to avoid risks that
have been identified.
Risk Event
A discrete occurrence that effects a
project.
Risk Evaluation
Process used to determine risk management
priorities.
Risk Identification
Process of determining what could pose a
risk.
Risk Management
Systematic application of policies,
procedures, methods and practices to the tasks of identifying,
analyzing, evaluating, treating and monitoring risk (The
process whereby decisions are made to accept known or assessed
risks and /or the implementation of actions to reduce the
consequences or probability of occurrence)
Risk Management Plan
A document defining how Project Risk
Analysis and Management is to be implemented in the context of a
particular project.
Risk Matrix
A matrix with risks located in rows, and
with impact and likelihood in columns.
Risk Prioritizing
Ordering of risks according first to their
risk value, and then by which risks need to be considered for
risk reduction, risk avoidance, and risk transfer.
Risk Quantification
Process of applying values to the various
aspects of a risk (Evaluating the probability of risk event
effect and occurrence.)
Risk Ranking
Allocating a classification to the impact
and likelihood of a risk.
Risk Reduction
Action taken to reduce the likelihood and
impact of a risk.
Risk Register
Formal record of identified risks (A
body of information listing all the risks identified for the
project, explaining the nature of each risk and recording
information relevant to its assessment and management)
Risk Response
Contingency plans to manage a risk should
it materialize (Action to reduce the probability of the
risk arising or to reduce the significance of its detrimental
impact if it does arise).
Risk, Secondary
Risk that can occur as a result of treating
a risk
Risk Sharing
Diminution of a risk by sharing it with
others, usually for some consideration
Risk Transfer
A contractual arrangement between two
parties for delivery and acceptance of a product where the
liability for the costs of a risk is transferred from one party
to the other.
Risk Treatment
Selection and implementation of appropriate
options for dealing with risk
Top of Page
Safety Plan
The standards and methods which minimize to
an acceptable level the likelihood of accident or damage to
people or equipment
Schedule
A Schedule is the timetable for a project.
It shows how project tasks and milestones are planned out over a
period of time.
Schedule Control
Controlling schedule changes.
Schedule Dates
Start and finish dates calculated with
regard to resource or external constraints as well as project
logic.
Schedule Performance Index (SPI)
Ratio of work accomplished versus work
planned, for a specified time period. The SPI is an efficiency
rating for work accomplishment, comparing work accomplished to
what should have been accomplished.
Schedule Variance (cost)
The difference between the budgeted cost of
work performed and the budgeted cost of work scheduled at any
point in time.
Scheduled Finish
The earliest date on which an activity can
finish, having regard to resource or external constraints as
well as project logic.
Scheduled Start
The earliest date on which an activity can
start, having regard to resource or external constraints as well
as project logic.
Scheduling
Scheduling is the process of determining
when project activities will take place depending on defined
durations and precedent activities. Schedule constraints specify
when an activity should start or end based on duration,
predecessors, external predecessor relationships, resource
availability, or target dates.
Scope
The scope is the sum of work content of a
project.
Scope Change
Any change in a project scope that requires
a change in the project’s cost or schedule.
Scope Change Control
Controlling changes to the scope.
Scope Verification
Ensuring all identified project
deliverables have been completed satisfactorily.
Scope of Work
A description of the work to be
accomplished or resources to be supplied.
Secondary Risk
The risk that may occur as a result of
invoking a risk response or fallback plan.
Secondment Matrix
An organizational structure whereby team
members are seconded from their respective departments to the
project and are responsible to the project manager
S-Curve
A display of cumulative costs, labor hours
or other quantities plotted against time.
Sequence
Sequence is the order in which activities
will occur with respect to one another.
Slack
Calculated time span within which an event
has to occur within the logical and imposed constraints of the
network, without affecting the total project duration. Note 1:
It may be made negative by an imposed date. Note 2. The term
slack is used as referring only to an event.
Slip Chart
A pictorial representation of the predicted
completion dates of milestones (also referred to as Trend Chart)
Slippage
The amount of slack or float time used up
by the current activity due to a delayed start or increased
duration.
Soft Project
A project that is intended to bring about
change and does not have a physical end product.
Soft Skills
Soft skills include team building, conflict
management and negotiation.
Source Selection
Choosing from potential contractors.
Splittable Activity
Activity that can be interrupted in order
to allow its resources to be transferred temporarily to another
activity
Sponsor
Individual or body for whom the project is
undertaken and who is the primary risk taker
Stage
A natural high level subsection of a
project that has its own organizational structure, life span and
manager.
Stage Payment
Payment part way through a project at some
predetermined milestone
Stakeholder
A person or group of people who have a
vested interest in the success of an organization and the
environment in which the organization operates (Project
stakeholders are people or organizations who have a vested
interest in the environment, performance and /or outcome of the
project.)
Start Event of a Project
Event with succeeding, but no preceding
activities. Note: There may be more than one start event
Start-To-Start Lag
Start-to-start lag is the minimum amount of
time that must pass between the start of one activity and the
start of its successor(s). This may be expressed in terms of
duration or percentage.
Starting Activity
A starting activity has no predecessors. It
does not have to wait for any other activity to start.
Statement of Work
A document stating the requirements for a
given project task
Status Reports
Written reports given to both the project
team and to a responsible person on a regular basis stating the
status of an activity, work package, or whole project. Status
Reports should be used to control the project and to keep
management informed of project status.
Steering Group
A body established to monitor the project
and give guidance to the project sponsor or project manager.
Subcontract
A contractual document which legally
transfers the responsibility and effort of providing goods,
services, data, or other hardware, from one firm to another.
Subcontractor
An organization that supplies goods or
services to a supplier
Subnet or Subnetwork
A division of a project network diagram
representing a subproject.
Subproject
A group of activities represented as a
single activity in a higher level of the same.
Success Criteria
Criteria to be used for judging if the
project is successful
Success Factors
Critical factors that will ensure
achievement of success criteria
Successor
A successor is an activity whose start or
finish depends on the start or finish of a predecessor activity.
Sunk Costs
Unavoidable costs (even if the project were
to be terminated)
Super-Critical Activity
An activity that is behind schedule is
considered to be super-critical. if it has been delayed to a
point where its float is calculated to be a negative value.
Supplier
Includes contractors, consultants and any
organization that supplies services or goods to the customer.
System
The complete technical output of the
project including technical products.
Systems and Procedures
Systems and procedure detail the standard
methods, practices and procedures of handling frequently
occurring events within the project.
Systems Management
Management that includes the prime
activities of systems analysis, systems design and engineering
and systems development.
Top of Page
Target Completion Date
A date which contractors strive toward for
completion of the activity.
Target Date
Date imposed on an activity or project by
the user. There are two types of target dates; target start
dates, and target finish dates.
Target Finish – Activity
Target Finish is the user's imposed finish
date for an activity. A Target Finish date is used if there are
pre-defined commitment dates.
Target Finish Date
The date planned to finish work on an
activity.
Target Finish – Project
A user's Target Finish date can be imposed
on a project as a whole. A Target Finish date is used if there
is a pre-defined completion date.
Target Start – Activity
Target Start is an imposed starting date on
an activity.
Target Start Date
The date planned to start work on an
activity.
Task
The smallest indivisible part of an
activity when it is broken down to a level best understood and
performed by a specific person or organization.
Team
A team is made up of two or more people
working interdependently toward a common goal and a shared
reward.
Team Building
The ability to gather the right people to
join a project team and get them working together for the
benefit of a project.
Team Development
Developing skills, as a group and
individually, that enhance project performance.
Team Leader
Person responsible for leading a team.
Technical Assurance
The monitoring of the technical integrity
of products.
Technical Guide
A document that guides managers, team
leaders and technical assurance coordinators on planning the
production of products.
Technical Products
Products produced by a project for an end
user.
Tender
A document proposing to meet a
specification in a certain way and at a stated price (or on a
particular financial basis), an offer of price and conditions
under which the tendered is willing to undertake work for the
client
Termination
Completion of the project, either upon
formal acceptance of its deliverables by the client and/or the
disposal of such deliverables at the end of their life
Terms of Reference
A specification of a team member’s
responsibilities and authorities within the project
Tied Activities
Activities that have to be performed
sequentially or within a predetermined time of each other
Time Analysis
The process of calculating the early and
late dates for each activity on a project, based on the duration
of the activities and the logical relations between them.
Time Based Network
A linked bar chart, a bar chart that shows
the logical and time relationships between activities
Time Limited Scheduling
Scheduling of activities, so that the
specified project duration, or any imposed dates are not
exceeded. Note: This may cause the envisaged resource levels to
be exceeded.
Time-Limited Resource Scheduling
The production of scheduled dates in which
resource constraints may be relaxed in order to avoid any delay
in project completion.
Time Now
Specified date from which the forward
analysis is deemed to commence (The date to which current
progress is reported. Sometimes referred to as the status date
because all progress information entered for a project should be
correct as of this date)
Time Recording
The recording of effort expended on each
activity in order to update a project plan.
Time-Scaled Logic Drawing
A drawing that displays the logical
connection between activities in the context of a time scale in
which each horizontal position represents a point in time.
Time-Scaled Network Diagram
A project network diagram drawn so that the
positioning of the activity represents schedule.
Time Sheet
A means of recording the actual effort
expended against project and non-project activities.
Top Down Cost Estimating
The total project cost is estimated based
on historical costs and other project variables and then
subdivided down to individual activities.
Total Float
Time by which an activity may be delayed or
extended without affecting the total project duration (Or
violating a target finish date)
Total Quality Management (TQM)
A strategic, integrated management systems
for customer satisfaction that guides all employees in every
aspect of their work.
Transit Time
Dependency link that requires time and no
other resources. It may be a negative time
Turnaround Report
A report created especially for the various
responsible managers to enter their progress status against a
list of activities that are scheduled to be in progress during a
particular time window.
Top of Page
Unlimited Schedule
Infinite schedule, schedule produced
without resource constraint
Users
The group of people who are intended to
benefit from the project
Top of Page
Value
A standard, principle or quality considered
worthwhile or desirable.
Value Management
A structured means of improving business
effectiveness that includes the use of management techniques
such as value engineering and value analysis.
Value Engineering
A technique for analyzing qualitative and
quantitative costs and benefits of component parts of a proposed
system
Value Planning
A technique for assessing, before
significant investment is made, the desirability of a proposal
based on the value that will accrue to the organization from
that proposal
Variance
A discrepancy between the actual and
planned performance on a project, either in terms of schedule or
cost.
Variance at Completion
The difference between Budget at Completion
and Estimate at Completion.
Variation
A change in scope or timing of work which a
supplier is obliged to do under a contract
Variation Order
The document authorizing an approved
technical change or variation
Top of Page
What-If Analysis
The process if evaluating alternative
strategies
What-if Simulation
Changing the value of the parameters of the
project network to study its behavior under various conditions
of its operation
Work
The total number of hours, people or effort
required to complete a task.
Work Breakdown Code
A code that represents the ‘family
tree’ of an element in a work breakdown structure.
Work Breakdown Structure
Way in which a project may be divided by
level into discrete groups for programming, cost planning and
control purposes. Note: see also ‘work package’ (The
WBS is a tool for defining the hierarchical breakdown of work
required to deliver the products of a project. Major categories
are broken down into smaller components. These are sub-divided
until the lowest required level of detail is established. The
lowest units of the WBS become the activities in a project. The
WBS defines the total work to be undertaken on the project and
provides a structure for all project control systems.)
Work Load
Work load is the amount of work units
assigned to a resource over a period of time.
Work Package
A group of related tasks that are defined
at the same level within a work breakdown structure (In
traditional cost/schedule systems, the criteria for defining
work packages is as follows: 1) Each work package is
clearly distinguishable from all other work packages in the
program. 2) Each work package has a scheduled start and finish
date. 3) Each work package has an assigned budget that is
time-phased over the duration of the work package. 4) Each work
package either has a relatively short duration, or can be
divided into a series of milestones whose status can be
objectively measured. 5) Each work package has a schedule
that is integrated with higher-level schedules).
Work Units
Work units provide the measurement units
for resources. For example, people as a resource can be measured
by the number of hours they work.
Top of Page
|